classic | mobile
 

Search...

SA Instrumentation & Control Buyers' Guide

Technews Industry Guide - IIoT 2018

Technews Industry Guide - Maintenance, Reliability & Asset Optimisation

 

Afrilek optimises boiler control at KwaZulu-Natal plant
June 2018, System Integration & Control Systems Design


UCL Company, a diverse agricultural operation based in Dalton, KwaZulu-Natal, has expertise in wattle bark extract exports, sugar cane production and pine lumber. The company identified a need to upgrade the controls on its boiler number 5 in order to replace the manual nature of the control. Furthermore, a need existed to optimise the process control of the boiler in order to reduce the use of coal and maximise the use of bagasse as a primary fuel source, thereby substantially reducing operating costs.

The existing system controlled the drum level, furnace pressure and master pressure of the boiler. The fuel feed motors and draught air fans were started manually from a control desk situated in the boiler control room. The existing system required a high level of operator interaction, but was not able to provide much information in terms of plant status.

The objectives of the project were to modernise, optimise the efficiency, and to create more transparency on the boiler. UCL approached Afrilek to provide a solution to benefit the production, maintenance and management teams. According to Afrilek’s Grant Douglas, the engineering manager at UCL – Ryno van Zyl – played a crucial role in demonstrating to management the needs and merits of the upgrade.

A race against time

The time factor was a major challenge for the team, with only three months being scheduled for all work, including design, procurement, installation and commissioning. Douglas explains that this process normally takes in excess of four months to complete. “Afrilek and the end user had to work closely together to complete the design in order to ensure that the equipment was delivered and installed before the deadline. We were able to overcome the challenges for two reasons: (1) our extensive experience on similar boiler upgrade projects and (2) by using standard Siemens Advanced Process Library (APL) templates.”

Project description

The end user already had Siemens PCS 7 installed onsite for the control of the pans, which included a redundant OS pair, engineering station and process historian. The boiler control system was integrated into the existing PCS 7 infrastructure after a new fibre optic network was installed throughout the plant to allow for future upgrades of other plant areas. The fibre network consisted of Siemens Scalance switches installed throughout the plant in a redundant ring structure.

To allow more availability of the operator stations, one of the OS servers was moved to a different location in the power house. This allowed for the operation of the plant even if there is a loss of communication to the pan floor or power house. A Siemens Scalance XR324 19-inch switch was used at the pan floor and was installed into the existing server cabinet housing the PCS 7 computers. Its modular nature will allow the end user to add more fibre or copper ports for future upgrades.

Siemens Scalance X308-2M switches were used at the balance of the locations (front-end, diffuser, 11 kV substation, power house, boilers and extract factory). The X308-2M is DIN rail mounted and also allows for expansion of ports for future upgrades. The switches are installed in a redundant ring structure and are all connected to UPS power to allow for high levels of availability. With the network infrastructure in place, a new Siemens S7400 CPU was installed in the power house to control both the boilers and the TAs in the power house. In addition, two new OS scada clients were installed, one for the operation and monitoring of Boiler 5, and one for the power house.

A new Siemens ET200M remote I/O station at the boiler integrates all the I/O from new Endress and Hauser instrumentation to the boiler MCC via Profinet. The exiting switchgear cabinets had to be retrofitted to allow for local and remote start of the starters as well as the indication and control of the starters from the PLC.

Afrilek provides UCL with 24-hour support on an ongoing basis. A VPN connection into the control system is used to provide remote support if the team is not onsite. All project objectives were successfully met within the stipulated timeframe.

For more information contact Grant Douglas, Afrilek, +27 (0)11 372 9340, grant@afrilek.com, www.afrilek.com


Credit(s)
Supplied By: Afrilek Automation
Tel: +27 11 372 9340
Fax: +27 11 453 1016
Email: sales@afrilek.com
www: www.afrilek.com
Share via email     Share via LinkedIn   Print this page

Further reading:

  • Giving back control to RCL Foods’ Pongola plant
    July 2018, Control Software Solutions, System Integration & Control Systems Design
    RCL Foods’ Pongola sugar mill is situated in northern KwaZulu-Natal and was operating a proprietary DCS that was installed in 1980. This obsolete and antiquated system resulted in unacceptable production ...
  • Controlling the IIoT
    Technews Industry Guide: Industrial Internet of Things & Industry 4.0, Schneider Electric South Africa, System Integration & Control Systems Design
    How the Industrial Internet of Things is changing the role of the control engineer.
  • Aspects to consider when securing ­industrial automation control system networks
    Technews Industry Guide: Industrial Internet of Things & Industry 4.0, RJ Connect, System Integration & Control Systems Design
    The most common examples are PLCs DCSs and scada systems. Such networks are known as industrial automation control systems. The main benefit of an IACS is that it allows greater efficiency by facilitating ...
  • Modern electromechanical machine design
    June 2018, Parker Hannifin - Sales Company South Africa, System Integration & Control Systems Design
    Engineers from the older generation will remember the days when machine design had to be based around catalogued electromechanical actuators. Variations from standard were rare, in addition to being expensive. ...
  • Ai2SA replaces HMI on legacy Mitsubishi A series PLC
    June 2018, Ai2SA, System Integration & Control Systems Design
    Architects Integrating Industry (Ai2SA), which specialises in ‘optimally managing and scoping industrial systems projects’, was recently contracted to replace a faulty HMI on a legacy Mitsubishi A Series ...
  • Yokogawa’s alarm shelving capability
    May 2018, Yokogawa South Africa, System Integration & Control Systems Design
    Alarm fatigue can desensitise operators to the extent that they may ignore a critical alarm with potentially disastrous consequences.
  • TwinCAT 3 Building Automation
    May 2018, Beckhoff Automation, System Integration & Control Systems Design
    The next generation in building control.
  • PSY Systems averts expensive shutdown
    April 2018, PSY International, System Integration & Control Systems Design
    Arc guard stops burn.
  • Working-at-height safety solution
    April 2018, System Integration & Control Systems Design, News
    Rope-access specialist Skyriders has provided a working-at-height safety solution for a contractor undertaking maintenance at the Sappi Ngodwana pulp and paper mill in Mpumalanga. It follows an earlier ...
  • Yokogawa’s revolutionary network-based control system
    April 2018, Yokogawa South Africa, System Integration & Control Systems Design
    Yokogawa’s unique portfolio for best-in-class scada solutions comprises of the versatile Stardom network-based control system (NCS), and the FAST/TOOLS supervisory HMI software platform.
  • Versatile signal conditioners
    April 2018, Phoenix Contact, System Integration & Control Systems Design
    Acquiring and processing analog signals of optimum quality.
  • Festo’s comprehensive asset optimisation, maintenance and energy efficiency solutions
    Technews Industry Guide: Maintenance, Reliability & Asset Optimisation 2018, Festo, Maintenance, Test & Measurement, Calibration, System Integration & Control Systems Design
    Festo’s technical experts and efficient technologies ensure that machines and systems have shorter downtime, consume fewer resources and less energy. This leads to increases in the sustainability of production processes and overall company productivity.

 
 
         
Contact:
Technews Publishing (Pty) Ltd
1st Floor, Stabilitas House
265 Kent Ave, Randburg, 2194
South Africa
Publications by Technews
Dataweek Electronics & Communications Technology
Electronic Buyers Guide (EBG)

Hi-Tech Security Solutions
Hi-Tech Security Business Directory

Motion Control in Southern Africa
Motion Control Buyers’ Guide (MCBG)

South African Instrumentation & Control
South African Instrumentation & Control Buyers’ Guide (IBG)
Other
Terms & conditions of use, including privacy policy
PAIA Manual





 

         
    classic | mobile

Copyright © Technews Publishing (Pty) Ltd. All rights reserved.