System Integration & Control Systems Design


Digital controllers - Part 3: The P term

October 2001 System Integration & Control Systems Design

In last month's issue, different aspects of the controllers' mathematical processes were touched on. In Part 3, the significance of the P term is explored.

Figure 1 shows a simplified P only controller. The P term may be considered as a pure amplifier that multiplies the input error signal by whatever gain (Kp) is set in the controller to produce the controller's output signal (PD). The bias allows the output to be manually adjusted either up or down between 50% and 100%.

Figure 1. The P only controller
Figure 1. The P only controller

Figure 2 shows a recording of a test on a P only controller with Kp = 4, with the controller mounted in the test rig as described in Part 2 of this series. A setpoint (SP) change of 10% has been made, which gives a step change of error of 10%, and the PD has immediately stepped up by 40%.

Figure 2
Figure 2

As there are no standards in PID controllers, manufacturers use various units for the P term. Probably the most common is 'gain', which as mentioned above is the amplifying factor, and is defined as the size of the output step divided by the size of the input step.

Another term used by quite a few manufacturers is 'proportional band'. The relationship between gain and proportional band is:

Proportional Band = (1/Gain) x 100%.

Proportional band is sometimes a useful concept in aiding one in explaining controller responses, as it may be considered as a graphical representation of the control range. This is illustrated in Figure 3, where a gain of 2 has been entered in a P only controller. The proportional band works out at 100/2 = 50%. This can be drawn as a band of 50% width lying around the setpoint. Note that the band need not be equidistant around the setpoint, but can in fact move around the setpoint. However, in ordinary controllers the band normally can never move away from the setpoint. (The position of where the setpoint lies within the band is in fact set by the value of the bias.)

Figure 3. Proportional band is 'graphical representation of control range'
Figure 3. Proportional band is 'graphical representation of control range'

Assume that at a particular moment of time the PV value was sitting on the bottom edge of the proportional band. This would mean that at that time the valve would be at one of its extremities, either fully open or fully shut. If the measurement were then to move up to the top of the proportional band, then the valve would have moved through its range to the opposite extremity. Thus the proportional band represents the control range, as control can only be achievable between the two valve extremities.

This leads to an interesting thought. In the first article in this loop signature series, it was mentioned that control performance or variance is a measure of error effectively totalised over a period of time. If we were able to put more gain into a controller and make the proportional band narrower, then it is feasible to believe that the variance would improve, as errors should be smaller in a narrower proportional band. Therefore the smaller the band, the better the variance, provided we could in fact achieve control within that band.

Taking this concept to a ridiculous extreme we could speculate that if we were to put an infinite gain into the controller, and make the proportional band infinitely small (ie zero), then we should have zero variance, as there should then be no control error. Infinite gain is of course ON/OFF control, and as we know, ON/OFF control is in fact in a continuous cycle, either switching the final control element fully on or off, as the PV rises and falls through setpoint. This results in very poor variance.

In reality as the gain is increased in the controller, the loop will eventually start reacting to changes in setpoint or load with a cyclic response, and this will get worse as the gain is increased. Therefore for minimum variance there is a balance between the amount of gain we can insert in a controller, and the amount of cycling that we would be prepared to tolerate in any particular control loop. The actual limit in practice would be where the gain in the controller would give rise to a quarter damped amplitude response on a step change in setpoint.

To explore the limitations inherent in a P only controller, take the practical case of such a controller that is often still encountered in level controls in plants. This is the ball valve. The ball valve and level process make up a complete feedback control loop. The ball is the measuring element. The arm connecting the ball to the valve is the proportional control mechanism, and the valve the final control element.

Imagine the system illustrated in Figure 4 is being used for controlling the level in the reservoir feeding water to our plant. When we come to examine the system, let us imagine that we find that the inflow and outflow are equal. The level is therefore constant at some particular point. Let us call this point our desired level, the setpoint. We then proceed to perform a little experiment, and open the manual valve controlling the flow of water to our plant by 10%. As the valve opens, the flow increases and the level starts dropping. As it does so, the ball drops with it and opens up its valve, which in turn increases the flow of inlet water.

Figure 4. P only controller example of the ball valve. Ball valve always ensures inflow equals outflow (balance point) initially, and by pure chance. PV was at desired SP, but if outflow is changed there will be an offset between SP and PV
Figure 4. P only controller example of the ball valve. Ball valve always ensures inflow equals outflow (balance point) initially, and by pure chance. PV was at desired SP, but if outflow is changed there will be an offset between SP and PV

Eventually the inflow will equal the outflow at which point the level stops dropping, and will remain constant. The control system is now in equilibrium, and the level will remain at the new value, as long as no further changes are made to the manual valve.

The level is again under control, but is no longer at setpoint, and we say that we are now controlling the level with an 'offset'. Offset is the main drawback to P only control. There is nothing in a P only controller that can do anything to permanently eliminate the offset. For practical purposes one can generally assume that a P only control system will almost definitely control with offset at some stage or other. In certain instances one can tolerate a certain amount of offset. However, the majority control loops are there to keep the process at the setpoint.

The best one can do with a P only controller is to minimise offset. This can be achieved in two ways. Firstly, if the controller gain is increased, the offset will decrease proportionally. Secondly, one can bring the process to the setpoint by adjusting the valve position manually. In the example of the ball valve above, one could physically bend up the arm between the ball and the valve to allow the level to come back up to the setpoint. In a real controller the same effect can be achieved by adjusting the bias. This adjustment is often called 'manual reset'.

The problem with manual reset is that if you had reset the offset at a particular point in time, then when changes occurred in the process again, another offset would result. In practice, manual reset is used only for initially setting up P only control systems.

In the real world of industrial process control, P only control should only be used on processes that are tuned with a large P gain value. It would generally be impossible to use it where the P value is small, as large offsets could result. Therefore one normally only finds P only controllers on integrating loops such as level controls where high controller P gain is normal.

Integrating loops are in actual fact better without the I term in the controller. There are two reasons for this. The first is that as mentioned in previous articles, any hysteresis on a valve on an integrating process that is controlled with P+I control will result in continuous cycling. The second reason is that the I term introduces a second integral term into the combined loop process transfer function, and prevents perfect pole cancellation tuning from being achieved. Therefore the only reason that one should technically ever use the I term in the controller on an integrating process, is if the possible offset is unacceptable. However, in reality, most people do not like processes being controlled with offset, even if it is actually acceptable, and as a result one finds that the I term is used on most integrating processes.

Michael Brown Control Engineering

(011) 486 0567

[email protected]

www.controlloop.co.za

Michael Brown is a specialist in control loop optimisation, with many years of experience in process control instrumentation. His main activities are consulting, and teaching practical control loop analysis and optimisation. He gives training courses that can be held in clients' plants, where students can have the added benefit of practising on live loops. His work takes him to plants all over South Africa, and also to other countries.



Credit(s)



Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

Major digital transformation project for Isuzu Motors
System Integration & Control Systems Design
Isuzu Motors South Africa, in partnership with NoMuda and S4 Integration, has kicked off a major two-year digital transformation project to modernise its production environment.

Read more...
Loop Signature Part 2-1: Loop signatures and process transfer functions
Michael Brown Control Engineering Fieldbus & Industrial Networking
The previous series of loop signature articles dealt with the basics of control loop optimisation, and concentrated on troubleshooting and ‘SWAG’ tuning of simple processes. In this new series, consideration will be given to dealing practically with more difficult issues like interactive processes, and with processes with much more complex dynamics.

Read more...
Modernising Vertical Filter Press Machines with Future-Focused Control Systems
System Integration & Control Systems Design
Project and Industry Pressure Filter Specialists approached us to modernise vertical filter press machines for the Minerals and Metals industry. The goal was to improve reliability, reduce downtime, ...

Read more...
Loop Signature 31: Non-linearity in control loops (Part 2)
Michael Brown Control Engineering Fieldbus & Industrial Networking
This article is a continuation of Loop Signature 30 published in the last issue in this series, exploring reasons for non-linearities which may be encountered in feedback control loops

Read more...
Project & industry
System Integration & Control Systems Design
Project and Industry This project involved delivering a complete electrical, instrumentation, and automation solution for a new OEM drum-twister machine, replacing an ageing unit in a major cabling production ...

Read more...
It’s a risky business not to challenge standard language
System Integration & Control Systems Design
On the surface, contracts all look alike. Once you’ve seen one, you’ve seen them all, or so it seems. Maybe so, but hidden within the standard language can be language that shifts the other party’s risk to you.

Read more...
Case History 200: The final case history – desuperheater control problem.
Michael Brown Control Engineering Editor's Choice Fieldbus & Industrial Networking
For this final article I have chosen to relate a problem that existed in a desuperheater temperature control on a boiler in a petrochemical refinery.

Read more...
Containerised Electrical & Control System Powers Paste Plant in Botswana
System Integration & Control Systems Design
Delivering a complete, containerized solution for a mine’s paste plant in Botswana, this project stands as a model of modern EC&I execution — integrating electrical, control, and automation systems into ...

Read more...
Loop Signature 30: Nonlinearity in control loops (Part 1)
Michael Brown Control Engineering Editor's Choice Fieldbus & Industrial Networking
If nonlinearity occurs it means that if one is to carry on controlling with the same response to changes in load or setpoint, then the tuning of the controller will also need to be adjusted to meet the new conditions.

Read more...
Control system upgrade: Smelting
SAM Systems Automation & Management System Integration & Control Systems Design
Systems Automation & Management recently completed a major control system upgrade in the smelting industry. The project was delivered on budget and achieved a positive ROI for the client.

Read more...









While every effort has been made to ensure the accuracy of the information contained herein, the publisher and its agents cannot be held responsible for any errors contained, or any loss incurred as a result. Articles published do not necessarily reflect the views of the publishers. The editor reserves the right to alter or cut copy. Articles submitted are deemed to have been cleared for publication. Advertisements and company contact details are published as provided by the advertiser. Technews Publishing (Pty) Ltd cannot be held responsible for the accuracy or veracity of supplied material.