Just-in-time approach for component delivery on green power plant

January 2026 Motion Control & Drives

Space is often the primary consideration when undertaking construction work at power plants. Modular construction techniques, along with the precise coordination and delivery of components to site, are the most effective methods to ensure power plant projects proceed smoothly. Mammoet was approached to assist EnBW in constructing a new power plant in Altbach/Deizisau, Germany. The new combined cycle gas turbine fuel-switch power plant will serve as a green energy facility, capable of operating on natural gas, hydrogen, or blends of the two, instead of coal.

Constructing a new power plant adjacent to an existing one posed a significant challenge, with maximising space and minimising disruption being the foremost priorities. To address these challenges, a just-in-time approach was implemented, which significantly alleviated congestion at the site during the construction process. Additionally, the construction of a temporary jetty enabled the main crawler crane to operate continuously, facilitating the offloading of the components and their subsequent installation.

Getting the heavy items to site, just in time

The initial challenge was determining how to transport the heavy items to the construction site and where to store them. Although a storage area was available on site, it was insufficient to accommodate the needs of this project. Faced with a large list of components to deliver and insufficient space to store them, Mammoet temporarily stored the largest items at its storage yard in Schiedam, the Netherlands. Transported to Schiedam by sea, the components were subsequently marshalled, stored, scheduled for delivery, and shipped to Altbach just-in-time on specialised river-going vessels. The river Neckar runs alongside the power plant, which has an existing jetty. However, utilising this jetty as a trans-shipment point was not feasible as it would have significantly interfered with the activities at the site.

Many complex components, very little space

Numerous components required storage and subsequent shipment to the site, including HRSG modules, a generator, a gas turbine, a transformer and stack modules. The 15 HRSG modules, weighing between 80 and 250 tons, presented a particular challenge due to their 30 metre length, which rendered them exceptionally fragile.

“It is a flexible module that does not tolerate deformation and therefore had to be kept perfectly straight at all times,” explains Leonid Sinelnikov, project manager at Mammoet. “We meticulously examined every stage of their handling to ensure they remained undamaged. This included ground preparation at Schiedam and the use of specialised lifting beams and rigging tools for their transportation and offloading.”

Two crawler cranes, a main 1350 ton crane and a 600 ton tailing crane, were utilised to tail up the HRSG modules from a horizontal to a vertical position. Additionally, the modules had to be lifted over the top of a building. Due to the extended length of the crane’s boom, clearance was required from Stuttgart Airport to execute the lift.

The installation of the 400 MW gas turbine presented another complex challenge. A late requirement specified that its base plate had to be perfectly level due to the construction of its supports. “This is not standard practice for a cargo exceeding 350 ton,” notes Sinelnikov. “Heavy steel rigging typically allows for some tolerances. Massive slings and grommets are never exactly the same length, which would not meet the precise tolerances required by the client.”

To address this, strand jacks were integrated into the crane’s rigging, enabling the team to level the unit during the lift prior to installation. The six stack modules, which combine to form a large chimney, were among the most logistically challenging components to deliver, as they had to be transported via a public road.

These sections were prefabricated offsite and transported using two 12-axle lines of Mammoet self-propelled modular transporters. The team identified the optimal route to minimise site modifications, conducting a 3D scan of the path from the fabrication site to the final installation location.

The modules, measuring up to 18 metres in height and weighing 95 tons, had to be elevated onto a support structure to provide sufficient clearance and reduce on-site preparations. Although the units needed to traverse just 75 metres of public road, a journey that could be completed in minutes, the preparation and planning required several weeks.

A genuine team effort

With numerous complex components needing to be delivered to an active site where multiple contractors were working simultaneously, success rested on meticulous planning, careful execution and clear communication. From the sales and planning teams to the engineers and the project team managing operations on the ground, it was a genuine team effort to deliver this comprehensive end-to-end solution.

For more information contact Jana Wolf, Mammoet, [email protected], www.mammoet.com




Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

Wind energy in the Black Forest
Motion Control & Drives
For more than 20 years, numerous wind turbines have stood in the Black Forest and are now receiving a performance boost through repowering projects.

Read more...
Kollmorgen advances linear motor safety and performance
Motion Control & Drives
Kollmorgen Corporation has released the next update for the SafeMotion Monitor (SMM) firmware, SMM 3.0. This upgrade expands functional safety support for linear motors and linear axes, helping machine builders implement functional safety in industrial applications that require safety.

Read more...
PC-based control for additive machine tools
Beckhoff Automation Motion Control & Drives
IRPD is a specialist in additive machine tools. Development is heavily focused on high system throughput and consistently high process quality. This goal was achieved with the help of PC- and EtherCAT-based control and drive technology from Beckhoff.

Read more...
Major software release for Parker PSD servo drives
Parker Hannifin - Sales Company South Africa Motion Control & Drives
Parker Hannifin has released its PSD servo drive family delivering new control modes, advanced synchronisation functions and performance optimisations designed to improve throughput, accuracy and system efficiency in demanding industrial applications.

Read more...
Robotic positioning system drastically reduces changeover times
Beckhoff Automation Motion Control & Drives
At the SLAC National Accelerator Laboratory in Menlo Park, California, an advanced robotic system by Square One Systems Design and Beckhoff speeds up high-energy physics experiments.

Read more...
Lubricant contamination costs more than you think
Motion Control & Drives
Lubrication Engineers has identified that 90% of lubrication contamination happens during storage and dispensing, not during application. To address this costly problem, it offers the isoPOD, a portable ‘plug and play’ lubrication storage and dispensing unit that’s a first for the South African market.

Read more...
New generation surface drill rig
Motion Control & Drives
Epiroc South Africa is launching a new and improved PowerROC T45. This new generation surface drill rig offers increased fuel efficiency and high availability, and is a welcome addition to the PowerROC family.

Read more...
How vision-guided robotics is transforming South African manufacturing
Yaskawa Southern Africa Motion Control & Drives
In South African manufacturing, the final stages of production need more than manual labour or conventional automation. For many, vision-guided robotics is becoming the solution to smarter, more flexible end-of-line processes.

Read more...
Transporting substations for the world’s largest offshore wind farm
Motion Control & Drives
Dogger Bank Wind Farm will be the world’s largest offshore wind farm when it is completed. Mammoet was involved in providing transportation and weighing of the project’s three offshore substations.

Read more...
Lubrication application a key component for wire rope longevity
Motion Control & Drives
As part of its extensive work to help develop benchmarking standards for wire rope lubrication in South Africa, lubrication specialists Lubrication Engineers South Africa has found the Viper wire rope lubricator to be a key element for effective lubrication application and rope maintenance.

Read more...









While every effort has been made to ensure the accuracy of the information contained herein, the publisher and its agents cannot be held responsible for any errors contained, or any loss incurred as a result. Articles published do not necessarily reflect the views of the publishers. The editor reserves the right to alter or cut copy. Articles submitted are deemed to have been cleared for publication. Advertisements and company contact details are published as provided by the advertiser. Technews Publishing (Pty) Ltd cannot be held responsible for the accuracy or veracity of supplied material.




© Technews Publishing (Pty) Ltd | All Rights Reserved