Motion Control & Drives


Actualising sustainability with Sibanye-Stillwater

Technews Industry Guide: Sustainable Manufacturing 2023 Motion Control & Drives

Energy Drive is proud to announce that Sibanye-Stillwater is predicted to achieve an energy saving of 60% from August 2021 to August 2031. This is made up of 374,02 GWh from its Shaft 8, Shaft 2 and the upcoming Shaft 5. This equates to 393,7 M kg of CO2, SOx, and NOx emissions reduced, 519,9 Megalitres of water saved, and 256,6 M kg less coal and ash.

The site uses multiple medium voltage (MV) ventilation fans to provide airflow to the mine. The two vent fans at the shaft are directly coupled to two 2240 kW induction motors – a standard squirrel cage motor and a slip ring motor. These fans ran in a duty/standby fashion (common of a ventilation fan system), with one fan running continuously to provide airflow to the shaft. The second fan was used as a standby fan to ensure redundancy. The fans were controlled from the mine’s central Wonderware scada network using inlet guide vanes (IGVs). A third-party energy partner managed the clipping schedule on behalf of the mine, which used the IGVs to reduce airflow during peak times.

When Sibanye and Energy Drive started collaborating, this shaft was quickly identified as a prime candidate for energy savings. Energy Drive engineers saw the opportunity to run both fans together to provide the same airflow as one fan.

While counterintuitive, this concept would allow Energy Drive to run each fan at a much lower speed. Each fan would provide a lower airflow, giving a substantial decrease in power demand. Additionally, running two fans with fully open IGVs allows the fans to return closer to their best operating point (BOP), allowing for greater efficiency. Using the mine’s suggested flow rates, the Energy Drive engineers predicted an energy saving of 60%.

The first challenge to overcome was one of space. Energy Drive’s solutions are typically mobile and self-contained. The VSDs intended for use at the mine were too tall for the typical high cube container, prompting project engineers to consider other solutions. With the benefit of being easily transportable and a familiar footprint for logistics companies – shipping containers were therefore utilised for this purpose. The decision was taken to use the same base dimensions as the 12 merer container, but with a bespoke e-Unit constructed on it. This allowed Energy Drive to accommodate the tall VSDs, while still having an easily mobile and self-contained solution.The electrical solution provided the mine with two modes of operation: VSD operation, and running the fans via their original DOL starters, which is achieved using ring main units (RMUs).

When the e-Unit was completed, a cold-commissioning of the VSDs was performed, and the unit was sent to site. It could then be placed down into its final location, and all the final terminations and cable work could be performed.

The communication between Energy Drive and the site PLC is crucial, as Energy Drive needs to give feedback to the mine on the state of the VSD and receive input from the mine on clipping/non-clipping modes of operation. The Energy Drive PLC can then also act to keep IGVs fully open when under VSD control, to maximise savings for the site.

A data and analytics platform allows Energy Drive engineers to have a live view of both the VSD health and the health of system communications. In the event of anything out of the ordinary, this data is at the fingertips of engineers who can inform mining personnel and dispatch technicians when needed.

A critical part of the commissioning process was establishing a flow baseline for the mine. This was done in collaboration with a third party, who performed a comprehensive set of pitot tube tests to determine the pressure when on IGV control. These tests were done during the clipping and non-clipping stages of operation. The VSD was then tested at three operating speeds, 30 Hz, 27 Hz and 24 Hz. Once all these tests had been performed, a comprehensive comparison between the flows while under IGV control and the flows while under VSD control could be made. The report showed that while under VSD, an operating speed of 27 Hz on each fan would provide the mine with the same flow received during non-clipping operations. Both fans could be run at 24 Hz during clipping times to achieve the same flow rates.

With an original baseline of 1710,3 kW, the fans now run at 605,75 kW. In fact, the results of this project have been so successful that Energy Drive was awarded the Energy Award for Industrial Energy Project of the Year by The Southern African Energy Efficiency Confederation (SAEEC) for 2021.




Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

WEBER-HYDRAULIK modernises warehouse in record time
Motion Control & Drives
WEBER-HYDRAULIK is a leading international specialist in customised hydraulic solutions. After its old buffer warehouse had become outdated and was partially worn out mechanically, the decision was made to completely renovate it.

Read more...
OMC deploys cobots to improve throughput ten times
Motion Control & Drives
OMC, a pioneer in optoelectronics design and manufacture, is investing to introduce innovative cobot technology onto its fibre optic production line.

Read more...
Yaskawa Southern Africa launches laser welding cell
Yaskawa Southern Africa Motion Control & Drives
Yaskawa Southern Africa has partnered with Industrial Manufacturing Systems South Africa to introduce the Megmeet laser welding cell, a breakthrough solution combining precision robotics with cutting-edge laser technology.

Read more...
Next-gen planetary gearboxes
SEW-EURODRIVE Motion Control & Drives
Leading the way in planetary gear unit innovation, SEW-EURODRIVE is extending its reach across a growing range of industries, delivering the advantages of this powerful technology through locally engineered solutions that ensure faster lead times.

Read more...
Record-breaking dragline relocation
Motion Control & Drives
Draglines are key pieces of equipment in open-pit mining. BHP Mitsubishi Alliance entrusted Mammoet with the relocation of a 3100 ton Marion 8050 dragline from one end of the Peak Downs coal mine in Queensland, Australia to another, a full 27 km away.

Read more...
igus expands 3D printing capabilities
igus Motion Control & Drives
Motion plastics specialist, igus South Africa has introduced a new 3D printing service capable of producing custom parts in two engineering-grade polymers with exceptional strength and without the need for lubrication.

Read more...
Bühler adds new die refurbishment machine
Motion Control & Drives
Bühler has reinforced its commitment to customers in southern Africa with the installation of a new die refurbishment machine at its Johannesburg workshop.

Read more...
SEW-EURODRIVE drives innovation at automotive plant
SEW-EURODRIVE Motion Control & Drives
[Sponsored] A major automotive manufacturer in Gauteng has boosted its operational efficiency, safety and energy savings with the installation of SEW-EURODRIVE’s advanced MOVIGEAR mechatronic drive system in its newly expanded buffering zone.

Read more...
Reimagining rotation for a circular and sustainable future
SKF South Africa Motion Control & Drives
Through the design and manufacture of components with sustainability at their core, SKF is reimagining the future of rotation, rolling away from traditional, consumable-based thinking toward a smarter, more sustainable circular approach.”

Read more...
Optimising operational efficiencies through advanced filtration systems
Bearing Man Group t/a BMG Motion Control & Drives
Filtration is the only effective defense against wear and tear when contaminants are present. It is therefore critical that effective filter components are correctly used to ensure dependable performance, high efficiency and extended service life of machinery and vehicles.

Read more...









While every effort has been made to ensure the accuracy of the information contained herein, the publisher and its agents cannot be held responsible for any errors contained, or any loss incurred as a result. Articles published do not necessarily reflect the views of the publishers. The editor reserves the right to alter or cut copy. Articles submitted are deemed to have been cleared for publication. Advertisements and company contact details are published as provided by the advertiser. Technews Publishing (Pty) Ltd cannot be held responsible for the accuracy or veracity of supplied material.




© Technews Publishing (Pty) Ltd | All Rights Reserved