System Integration & Control Systems Design


Afrilek optimises boiler control at KwaZulu-Natal plant

June 2018 System Integration & Control Systems Design

UCL Company, a diverse agricultural operation based in Dalton, KwaZulu-Natal, has expertise in wattle bark extract exports, sugar cane production and pine lumber. The company identified a need to upgrade the controls on its boiler number 5 in order to replace the manual nature of the control. Furthermore, a need existed to optimise the process control of the boiler in order to reduce the use of coal and maximise the use of bagasse as a primary fuel source, thereby substantially reducing operating costs.

The existing system controlled the drum level, furnace pressure and master pressure of the boiler. The fuel feed motors and draught air fans were started manually from a control desk situated in the boiler control room. The existing system required a high level of operator interaction, but was not able to provide much information in terms of plant status.

The objectives of the project were to modernise, optimise the efficiency, and to create more transparency on the boiler. UCL approached Afrilek to provide a solution to benefit the production, maintenance and management teams. According to Afrilek’s Grant Douglas, the engineering manager at UCL – Ryno van Zyl – played a crucial role in demonstrating to management the needs and merits of the upgrade.

A race against time

The time factor was a major challenge for the team, with only three months being scheduled for all work, including design, procurement, installation and commissioning. Douglas explains that this process normally takes in excess of four months to complete. “Afrilek and the end user had to work closely together to complete the design in order to ensure that the equipment was delivered and installed before the deadline. We were able to overcome the challenges for two reasons: (1) our extensive experience on similar boiler upgrade projects and (2) by using standard Siemens Advanced Process Library (APL) templates.”

Project description

The end user already had Siemens PCS 7 installed onsite for the control of the pans, which included a redundant OS pair, engineering station and process historian. The boiler control system was integrated into the existing PCS 7 infrastructure after a new fibre optic network was installed throughout the plant to allow for future upgrades of other plant areas. The fibre network consisted of Siemens Scalance switches installed throughout the plant in a redundant ring structure.

To allow more availability of the operator stations, one of the OS servers was moved to a different location in the power house. This allowed for the operation of the plant even if there is a loss of communication to the pan floor or power house. A Siemens Scalance XR324 19-inch switch was used at the pan floor and was installed into the existing server cabinet housing the PCS 7 computers. Its modular nature will allow the end user to add more fibre or copper ports for future upgrades.

Siemens Scalance X308-2M switches were used at the balance of the locations (front-end, diffuser, 11 kV substation, power house, boilers and extract factory). The X308-2M is DIN rail mounted and also allows for expansion of ports for future upgrades. The switches are installed in a redundant ring structure and are all connected to UPS power to allow for high levels of availability. With the network infrastructure in place, a new Siemens S7400 CPU was installed in the power house to control both the boilers and the TAs in the power house. In addition, two new OS scada clients were installed, one for the operation and monitoring of Boiler 5, and one for the power house.

A new Siemens ET200M remote I/O station at the boiler integrates all the I/O from new Endress and Hauser instrumentation to the boiler MCC via Profinet. The exiting switchgear cabinets had to be retrofitted to allow for local and remote start of the starters as well as the indication and control of the starters from the PLC.

Afrilek provides UCL with 24-hour support on an ongoing basis. A VPN connection into the control system is used to provide remote support if the team is not onsite. All project objectives were successfully met within the stipulated timeframe.

For more information contact Grant Douglas, Afrilek, +27 (0)11 372 9340, [email protected], www.afrilek.com



Credit(s)



Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

Control system upgrade: Smelting
System Integration & Control Systems Design
Systems Automation & Management recently completed a major control system upgrade in the smelting industry. The project was delivered on budget and achieved a positive ROI for the client.

Read more...
Gottwald drives upgrade: Ports and harbours
Abacus Automation System Integration & Control Systems Design
In the ports and harbours sector, Abacus Automation completed a significant modernisation of a Gottwald crane, improving both operational reliability and serviceability.

Read more...
Mining industry upgrade: From ageing systems to maximum capacity
System Integration & Control Systems Design
Iritron recently undertook a major upgrade in the mining sector, focusing on washing and screening plants, jigs, thickeners, tailings, water systems, conveyors and reclaimers.

Read more...
Agogo Integrated West Hub Project: FPSO/subsea offshore Angola
System Integration & Control Systems Design
The Agogo Integrated West Hub project represents a historic milestone in the FPSO and subsea industry, achieving first oil offshore of Angola. This project is the first FPSO deployment since ANPG’s establishment in 2019, and the first major project for Azule Energy since 2022.

Read more...
Digital transformation from the edge
DirectLogic Automation System Integration & Control Systems Design
Edge-enabled PLCs are an accessible and affordable way for most users to collect and create value from use field-sourced data.

Read more...
Powering southern Africa’s industrial evolution for over five decades
Oilpower System Integration & Control Systems Design
Established in 1974, Oilpower is a recognised name in South Africa’s hydraulic and pneumatic sector. What started as a small, family-run business has matured into a highly structured operation with specialised teams, experienced engineers and a reputation for technical excellence and reliability. Oilpower is celebrating its 50th anniversary this year

Read more...
Metal plant automation upgrade
ABB South Africa System Integration & Control Systems Design
A combined compressor house (CCH) control system replacement project, undertaken by NJC, an ABB Authorised Value Provider (AVP), has won high praise from client ArcelorMittal.

Read more...
SIs - the channel’s conductors of light
Schneider Electric South Africa System Integration & Control Systems Design
Today’s original equipment manufacturers are innovators in the truest sense, driving the absolute newest in technological advancement. While they develop advanced and often groundbreaking solutions, it is the system integrators who bring these innovations to life.

Read more...
The state of the SI industry remains strong and is expanding
System Integration & Control Systems Design
The system integration (SI) industry is expanding with the adoption of AI, automation and data sharing, allowing companies to improve operational efficiency and competitiveness across diverse sectors.

Read more...
The symbiotic relationship between OEMs and SIs
Schneider Electric South Africa Editor's Choice System Integration & Control Systems Design
While businesses tend to turn directly to original equipment manufacturers OEMs or vendors when embarking on IT projects, the role of the SI as a key facilitator and partner cannot be overstated.

Read more...









While every effort has been made to ensure the accuracy of the information contained herein, the publisher and its agents cannot be held responsible for any errors contained, or any loss incurred as a result. Articles published do not necessarily reflect the views of the publishers. The editor reserves the right to alter or cut copy. Articles submitted are deemed to have been cleared for publication. Advertisements and company contact details are published as provided by the advertiser. Technews Publishing (Pty) Ltd cannot be held responsible for the accuracy or veracity of supplied material.




© Technews Publishing (Pty) Ltd | All Rights Reserved