System Integration & Control Systems Design


Coal handling plant replaces scada system

May 2000 System Integration & Control Systems Design

Industrial System Integrators (ISI) was commissioned by the Project and Technology Services (P&TS) department of Sasol Coal to handle the replacement of the scada software and related activities as part of a control system upgrading project. ISI's scope included installation of the scada software, the setting up and configuration of the software, the drafting of mimics and finally the commissioning of the software. The work was required to ensure optimum operation of the Sasol Coal Supply (SCS) plant.

Sasol Coal operates a comprehensive coal handling plant in Secunda, which consists of six stockpiles, each being served by a stacker and a reclaimer. A number of conveyers interconnect the stockpiles with each other. The stockpiles are supplied with coal from seven underground mines, one opencast mine and a coal beneficiation plant. The coal from these sources is transported with long overland conveyors to the stockpiles. The coal on the stockpiles is used as feedstock for the Sasol Synthetic Fuels plant in Secunda.

The SCS plant is controlled with Mitsubishi PLCs. Previously, they were connected to two control rooms via Conet networks. The final interface to the operating personnel was achieved by means of a number of Mul-T-Link scada packages running on industrial type 486 PCs.

SCS decided to upgrade the control systems - ISI was awarded the contract to complete commissioning of the scada part by the end of 1999. ISI handed the project over to P&TS on 15 December 1999 and this is how:

ISI draughted and got approved a comprehensive functional design specification (FDS). They also recommended a hardware platform that would suit the FDS. ISI replaced the Mul-T-Link packages with Citect Software, which was sized to include for possible future expansions to the system without major alterations to the proposed system and still provide full redundancy. Citect was also set-up so that it could easily interface to a management information system and a G2 simulation package.

The scada hardware platform is in a client/server configuration, which includes hot standby servers and makes bump-less transfer possible. The plant was divided into four geographical separate parts with each part being controlled from its own input/output (I/O) server. Each of the I/O servers also acts as hot standby for one of the other I/O servers. Alarms, trends and reports (ATR) on the system, are handled by a separate ATR server with its own hot standby. The hardware is completed by four separate servers for file handling, management information system, G2 and a network monitoring facility. ISI configured the system at the design stage to allow future expansion, should it be required.

Interface with operators is via a minimum of 10 workstations, a supervisor's workstation and a separate engineering workstation with a full access to all facilities on the system. Every workstation is able to address every server and hot standby server; all interfacing between servers, the workstations and the PLCs is via Ethernet. The system can also be remote accessed from any workstation on the office network at SCS.

A separate Citect package running on a freestanding server acts as back-up system to the main system. This 'secondary network' system connects via a Mitsubishi proprietary network to all the mission critical PLCs on the plant. The 'secondary network' server can be used to control the vital parts of the plant should the main networks fail. The system uses the same mimic screens as the main system.

The scada configuration meant that Citect was installed on the machines for the first time. All configuration of Citect was according to the FDS. The draughting of the mimic screens, workstation server connectivity, set up of the database for alarms, events, trending, logs, security and reporting needed to be completed in a minimum time frame with no downtime and full redundancy.

Allowance was made for the development of at least 200 screens with a maximum of one overall screen for the total plant. The screens for each section of the plant were developed with a minimum quantity of screens applicable to the information in that area of the plant.

Screens were developed for geographical areas, area start/stop, trajectory, mine bunker, factory bunker and the 10 000 t bunker. Various geographical screens that prevented control from that screen and allowed control from other screens, machine screens, stockpile screens, scale screens, ash and moisture analysis, electrical reticulation, weather stations, control room monitoring, utility, reports, daily downtime and production, alarms, exceptions and events, trending, scada configuration.

ISI had to assist the project team of Sasol Coal to write a proper driver for the PLC programs that would be capable of communicating with Citect and that would recover after fault conditions.

The project had to be undertaken as a brownfield one, which implied that the work had to be done on a producing plant and not on a new plant, and commissioning had to be done with minimum disruption to production. This was achieved successfully. Sasol were adamant that there would be zero production loss tolerated on the factory feeding system. Using Citect software it was possible and no production time was lost.

Roger Girdler of ISI stated that the project was one that took dedication from the ISI engineers and designers as they had to be available on site at all times during commissioning and for a minimum of two days after commissioning. The engineers worked hard to complete the project two weeks ahead of schedule and successfully handed it over to SCS on 15 December 1999.

ISI was, in the meantime, also commissioned to investigate the whole matter of the management information system and the G2 package. As part of that investigation they have to again draft an FDS. The work was scheduled to be completed by May 2000.





Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

SCiBOTRON’s quality culture the key to success
May 2020 , System Integration & Control Systems Design
The company was founded on lean principles and quickly grew into a QSE (Qualifying Small Enterprise). Ricardo Paddy, managing director and founding member, attributes one of the reasons for the company’s ...

Read more...
PC-based control technology for process automation
May 2020, Beckhoff Automation , System Integration & Control Systems Design
Progress is not based on the innovative creation of buzzwords. Unfortunately, the development of enabling technologies in recent decades did not help to raise process automation to an advanced level. ...

Read more...
Improved production capacity and efficiency
May 2020, Omron Electronics , System Integration & Control Systems Design
Automation with robotics increases production of chocolate by 40%.

Read more...
PCS Global keeps Dairymaid production on track
May 2020, PCS Global , System Integration & Control Systems Design
Commonly known as ‘the smile maker’, Dairymaid’s ice cream has been a favourite in many South African households for the past three decades. Keeping the factory running and ensuring the quality of the ...

Read more...
The efficient and easy to configure DALI-2 lighting solution
May 2020, Beckhoff Automation , System Integration & Control Systems Design
The TwinCAT 3 Lighting Solution, which is easy and convenient to configure via Excel files, simplifies all work steps from engineering to maintenance. All typical lighting controls are integrated in the ...

Read more...
Business unusual
May 2020, Autotronix , System Integration & Control Systems Design
Is it the right time to migrate your legacy servo and control hardware?

Read more...
Flexibility of PC-based control minimises development times
May 2020, Beckhoff Automation , System Integration & Control Systems Design
The outbreak of Covid-19 in China created a massive demand for masks and other medical products. Xiamen Booltech recognised the need to produce N95 masks, which provide protection for both medical staff ...

Read more...
Water management from Siemens optimises flood control
April 2020, Siemens Digital Industries , System Integration & Control Systems Design
The Erftverband is an organisation that includes municipalities, counties, industry and utilities, and as a public corporation it is responsible for cleaning private and industrial wastewater along the ...

Read more...
High-end measurement technology drives innovation in machine availability
Technews Industry Guide: Maintenance, Reliability & Asset Optimisation 2020, Beckhoff Automation , System Integration & Control Systems Design
EtherCAT measurement modules now include the cost-effective ELM314x Economy line.

Read more...
Enabling an energy-efficient HVAC system for a hypermarket
March 2020, RJ Connect , System Integration & Control Systems Design
Heating, ventilation and air conditioning (HVAC) is the technology of indoor and vehicular environmental comfort. HVAC systems are mostly used in hypermarkets to provide shoppers comfort and acceptable ...

Read more...