System Integration & Control Systems Design


Automation and information solution for Morupule Colliery

November 2012 System Integration & Control Systems Design

Royal HaskoningDHV (formerly SSI Engineers and Environmental Consultants) in Cape Town, in partnership with ADP Projects, has been working on the Morupule Colliery Expansion project since 2009. ADP Projects is the appointed engineering contractor and Royal HaskoningDHV was appointed to complete the electrical and electronic designs for this coal expansion project. Royal HaskoningDHV’s involvement began in the pre-feasibility phase and has continued through feasibility, detailed design and implementation. The company is currently in the final stages of the commissioning.

The colliery is situated in Palapye, eastern Botswana, and delivers coal to the Morupule Power Station currently being upgraded by the Botswana Power Corporation to 600 MW. The mine is an underground operation with access down an incline shaft to a depth of approximately 80 m. The underground infrastructure is being expanded in order to deliver sufficient coal to the new crushing and screening plant, associated surface stockpile capacity is also being expanded.

Project scope

The scope of the project is to upgrade the existing mining infrastructure, materials handling systems and processing plant in order to increase coal production from 1 to 3,2 million tons per annum. The upgrade will eventually result in an electrical load increase for the mine from 4 to 16 MVA.

The electronic scope of the project included the full specification and design of:

* Field instrumentation for the plant and underground coal mine.

* Plant and mining Mitsubishi PLC control systems.

* Conveyor control systems (safe and hazardous areas).

* Automatic fail-over centralised Adroit Scada visualisation system.

* Building and conveyor fire detection system.

* Underground voice communication system.

* Office and production ICT system.

* New buildings access control system.

* Scopes, bills and technical datasheets for the procurement of the various systems.

Royal HaskoningDHV also performed the following activities:

* Technical adjudication of tenders for all electronic equipment/systems.

* Quality management of all the equipment/systems during manufacturing.

* Factory acceptance testing in order to ensure that build was according to design.

* Technical support to the contractors and project staff on site during the construction and commissioning phases of the project.

Problem and challenges

Traditionally C&I projects focus almost entirely on the system control and instrumentation aspects. The Morupule project’s challenge to the C&I team was maximum use of the limited space and access available in a coal mine as well as to implement the solution during a limited shutdown window while complying with all statutory standards and guidelines for hazardous area installations. In addition to these challenges, the team also had to take existing systems, equipment standards and relatively low on-site engineering skills into consideration during the specification and design phases. The specific challenge was to ensure high availability of a control system that would be deployed over a 14 km fibre optic network.

Design approach

The INCOSE systems engineering approach was followed which included determining the project and system functional, physical and interface requirements. This is a common approach used throughout the systems engineering field and the use of contextual analysis of the entire system resulted in the identification and specification of all system interfaces, a challenge when dealing with a large quantity of vendor supplied control systems and black box solutions.

A hazardous zoning study was completed by specialists with the assistance of the project team. The result of this collaboration was that the mobile characteristics of the mining equipment were included in the zoning study, which became a key driver during system equipment and cabling selection. The probability and impact of risks were determined during this study and appropriately mitigated.

Specific challenges were encountered during the selection and specification of instrumentation and equipment for underground hazardous areas. These were overcome by constant communication with experts in the field that included Dimako Transformers, Explolabs and SAFA (South African Flameproof Association). In line with the risk-based approach all flameproof power centres were equipped with a local flammable gas sensor that back-trips the supply equipment through the pilot protection system.

Automation solution

A common services fibre optic infrastructure solution was selected for the mine-wide communications network as it catered for network flexibility, use in hazardous environments and network segment lengths that ranged from 500 to 1700 m.

The automation solution consists of a Mitsubishi System Q PLC for the underground mine networked via Profibus DP to remote I/O panels. An additional PLC handles the new crushing and screening plant networked via Melsecnet to the remote I/O. Mitsubishi System Q PLCs were also incorporated into two flameproof power centres for the remote control and monitoring of electrical loads.

The underground network is arranged in a self-healing fibre optic ring topology that extends into the underground workings and returns via the cable shafts and the 11 kV overhead transmission lines to the centralised control room.

Extensive use was made of fibre optic infrastructure for the underground mine. A single 12 core fibre optic cable is reticulated underground that carries the services for communications to the PLC, continuous miners, variable speed drives and intelligent conveyor head end controllers. Fibre optic reels were deployed to cater for the mobile nature of the continuous miners and flameproof power centres. All PLCs are networked via industrial Ethernet back to the Adroit Server cluster.

The intelligent conveyor head end controllers are remotely monitored and activated from the mining system PLC, achieved through a Modbus communications link to each head end controller.

Project statistics

* Total fibre optic cable installed: 14 km.

* Instrumentation number increase: 48 to 320.

* IO count increase: 250 to 1243.

* C&I project capital estimate: R31 million.

* Number of PLCs: 8.

* Number of remote IO panels: 20.

* Number of telemetry outstations: 6.

Project benefits

* Compliance with hazardous zoning requirements.

* Improved operator interfaces to the plant and mining equipment systems.

* Improved troubleshooting capabilities.

* High availability control networks.

* Software standards are in place for future use. The software configuration process involved the creation of functional design specifications for both the scada and PLC systems. Standardised software blocks were designed and programmed by Megadrive Automation, the SI for the project.

* Network architecture flexibility. The fibre optic network deployed underground includes fibre optic reel technology to cater for mobile equipment.

* The use of common infrastructure reduced costs. The automation system, fire detection and continuous miners communication services are catered for within a single fibre optic cable.

* Improved sharing of production data with other plant stakeholders.

* Improved production reporting with the introduction of Opus reports.

For more information contact Alfred Schroder, Royal HaskoningDHV, +27 (0)21 936 7600, www.rhdhv.co.za



Credit(s)



Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

Understanding the role of AI in generative engineering design
System Integration & Control Systems Design
When a design engineer sets out to design a new part, component, or assembly, the intent is to meet the design requirements for fit, form and function, and also incorporate a certain degree of innovation and elegance to the overall design. There is no reason to re-invent the wheel by introducing a new design.

Read more...
PCS stays up so you don’t have to
PCS Global System Integration & Control Systems Design
Maybe it’s time to look at a solution that stays online 99,99999% of the time so you don’t have to. This the world of Stratus computer platforms, tailor-made for your critical applications.

Read more...
Four ways the global parts shortage has led to innovation and openness
System Integration & Control Systems Design
For those who use automation parts, the unpredictable nature of the supply chain is one of the biggest problems faced today. The shortfall has impacted every industry, but automation components have been especially affected.

Read more...
Iritron’s year of consolidation
Iritron Editor's Choice System Integration & Control Systems Design
Despite the multiple challenges faced by businesses in South Africa, the buoyancy of the technology sector worldwide has produced some green shoots for automation specialist, Iritron.

Read more...
Five edge opportunities for SIs to maximise revenue in 2024
Editor's Choice System Integration & Control Systems Design
System integrators continue to face the challenge of doing more with less – supporting complex operations, while meeting production schedules with limited resources, and innovating to increase efficiency, maximise safety and reduce risk.

Read more...
Condition monitoring in a forging press retrofit
Beckhoff Automation System Integration & Control Systems Design
Significantly increased vibration on machines can result in many forms of negative impacts such as reduced system performance or damage to the machine and foundation. Using the example of retrofitting a forging press with a maximum press force of 2000 tons, Wölfel Engineering explains how efficiently the process was tailored and implemented with PC-based control and measurement technology from Beckhoff.

Read more...
System integration in the digital age
System Integration & Control Systems Design
To meet the challenges of an increasingly competitive marketplace, many manufacturers (end users) must focus on their core competencies and outsource the rest to experts.

Read more...
Choosing a system integrator
Editor's Choice System Integration & Control Systems Design
Automation is an essential part of manufacturing today. Whatever the size, an upgrade or migration project can be complex, and the risks can be high. This is where system integrators (SIs) can help. They can bring together complex subsystems or components of a larger system and make them operate as a whole.

Read more...
Iritron awarded international contract for furnace control
Iritron System Integration & Control Systems Design
Iritron has been awarded two international, multimillion-Rand furnace drying projects. The company has extensive expertise in furnace drying control systems, and provides solutions in the fields of electrical, instrumentation, control systems, and decision support systems.

Read more...
Capitalise on risks by turning them into opportunities for growth
Iritron System Integration & Control Systems Design
In spite of the challenges facing the global and local economy, systems integration expert, Iritron remains optimistic for the year ahead, and believes that there are significant opportunities to be found during a challenging economic climate.

Read more...