Afrilek optimises boiler control at KwaZulu-Natal plant

June 2018 System Integration & Control Systems Design

UCL Company, a diverse agricultural operation based in Dalton, KwaZulu-Natal, has expertise in wattle bark extract exports, sugar cane production and pine lumber. The company identified a need to upgrade the controls on its boiler number 5 in order to replace the manual nature of the control. Furthermore, a need existed to optimise the process control of the boiler in order to reduce the use of coal and maximise the use of bagasse as a primary fuel source, thereby substantially reducing operating costs.

The existing system controlled the drum level, furnace pressure and master pressure of the boiler. The fuel feed motors and draught air fans were started manually from a control desk situated in the boiler control room. The existing system required a high level of operator interaction, but was not able to provide much information in terms of plant status.

The objectives of the project were to modernise, optimise the efficiency, and to create more transparency on the boiler. UCL approached Afrilek to provide a solution to benefit the production, maintenance and management teams. According to Afrilek’s Grant Douglas, the engineering manager at UCL – Ryno van Zyl – played a crucial role in demonstrating to management the needs and merits of the upgrade.

A race against time

The time factor was a major challenge for the team, with only three months being scheduled for all work, including design, procurement, installation and commissioning. Douglas explains that this process normally takes in excess of four months to complete. “Afrilek and the end user had to work closely together to complete the design in order to ensure that the equipment was delivered and installed before the deadline. We were able to overcome the challenges for two reasons: (1) our extensive experience on similar boiler upgrade projects and (2) by using standard Siemens Advanced Process Library (APL) templates.”

Project description

The end user already had Siemens PCS 7 installed onsite for the control of the pans, which included a redundant OS pair, engineering station and process historian. The boiler control system was integrated into the existing PCS 7 infrastructure after a new fibre optic network was installed throughout the plant to allow for future upgrades of other plant areas. The fibre network consisted of Siemens Scalance switches installed throughout the plant in a redundant ring structure.

To allow more availability of the operator stations, one of the OS servers was moved to a different location in the power house. This allowed for the operation of the plant even if there is a loss of communication to the pan floor or power house. A Siemens Scalance XR324 19-inch switch was used at the pan floor and was installed into the existing server cabinet housing the PCS 7 computers. Its modular nature will allow the end user to add more fibre or copper ports for future upgrades.

Siemens Scalance X308-2M switches were used at the balance of the locations (front-end, diffuser, 11 kV substation, power house, boilers and extract factory). The X308-2M is DIN rail mounted and also allows for expansion of ports for future upgrades. The switches are installed in a redundant ring structure and are all connected to UPS power to allow for high levels of availability. With the network infrastructure in place, a new Siemens S7400 CPU was installed in the power house to control both the boilers and the TAs in the power house. In addition, two new OS scada clients were installed, one for the operation and monitoring of Boiler 5, and one for the power house.

A new Siemens ET200M remote I/O station at the boiler integrates all the I/O from new Endress and Hauser instrumentation to the boiler MCC via Profinet. The exiting switchgear cabinets had to be retrofitted to allow for local and remote start of the starters as well as the indication and control of the starters from the PLC.

Afrilek provides UCL with 24-hour support on an ongoing basis. A VPN connection into the control system is used to provide remote support if the team is not onsite. All project objectives were successfully met within the stipulated timeframe.

For more information contact Grant Douglas, Afrilek, +27 (0)11 372 9340, [email protected], www.afrilek.com



Credit(s)



Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

Flotation system modernisation for a gold processing and mineral recovery plant.
Moore Process Controls System Integration & Control Systems Design
Moore Process Controls has successfully modernised a gold processing plant's flotation control system, replacing obsolete I/O hardware with Schneider Electric's latest M580 X80 platform.

Read more...
Project and industry
Schneider Electric South Africa System Integration & Control Systems Design
Transforming crushing plant operations through integrated automation.    Controlgear Instramac was engaged to deliver the electrical control and automation systems for a new crushing plant within the ...

Read more...
Project and industry
EXEL Electrical Engineering System Integration & Control Systems Design
EXEL EE was contracted to deliver the complete electrical, control and instrumentation scope for the upgrade of a gold mine's water treatment facilities in Tanzania.

Read more...
Turning system integrators into trusted technology partners
Schneider Electric South Africa IT in Manufacturing System Integration & Control Systems Design
Schneider Electric’s Alliance Partner Programme is repositioning system integrators from hardware suppliers into lifecycle-value partners. Oriel Soupen explains the competency framework, certification model and real-world results that are already helping African system integrators win higher-value, longer-term engagements.

Read more...
When digital twins move from concept to critical tool
IT in Manufacturing System Integration & Control Systems Design Maintenance, Test & Measurement, Calibration
Digital twins are moving out of the lab and onto the mine, the factory floor and the transport network where they predict failures before they happen. Amritesh Anand looks at where they earn their keep, the data and integration work behind them, and the security questions every organisation should ask before switching one on.

Read more...
Best practices for managing the MRO supply chain in Africa
RS South Africa System Integration & Control Systems Design
RS South Africa outlines how strong data governance and digital tools can turn maintenance, repair and operations procurement into a strategic advantage across Africa.

Read more...
Containerised Solar Solution Accelerates Delivery of Riverside 3 MW Power Plant
Proconics System Integration & Control Systems Design
Proconics was engaged by NewFields to deliver the electrical integration solution for the Riverside 3 MW Solar Power Plant in Zimbabwe. The project required a compact, modular approach that could simplify deployment, minimise site works, and support rapid commissioning in a remote location.

Read more...
Modern Energy Metering Solution Enhances Reliability and Reporting for Major Power Utility
SAM Systems Automation & Management System Integration & Control Systems Design
This project involved the implementation of a modern energy metering system for a major power utility operating within the industrial automation and energy management sector. The objective was to improve the reliability, accessibility, and accuracy of energy data while simplifying infrastructure and reducing system complexity.

Read more...
PCS Global
PCS Global System Integration & Control Systems Design
PCS Global led a digital infrastructure initiative in a southern African data centre setting, aiming to merge several essential operational systems into one cohesive platform. The objective was to break down silos, enable real-time decisions, and ensure seamless operation in a mission-critical environment.

Read more...
Seamless migration from ET 200M to ET 200SP HA for future-ready automation
Moore Process Controls System Integration & Control Systems Design
Moore Process Controls undertook a modernisation initiative spanning the mining, petrochemical, and oil & gas sectors. This project involved upgrading legacy Siemens ET200M I/O systems to the advanced ET200SP HA platform.

Read more...









While every effort has been made to ensure the accuracy of the information contained herein, the publisher and its agents cannot be held responsible for any errors contained, or any loss incurred as a result. Articles published do not necessarily reflect the views of the publishers. The editor reserves the right to alter or cut copy. Articles submitted are deemed to have been cleared for publication. Advertisements and company contact details are published as provided by the advertiser. Technews Publishing (Pty) Ltd cannot be held responsible for the accuracy or veracity of supplied material.




© Technews Publishing (Pty) Ltd | All Rights Reserved