Nick Denbow's European report: The politics in power

December 2015 News

The combined effects of the erratic price of oil and natural gas supplies, modern environmental legislation requiring old polluting coal fired power stations to close down, and the UK planning laws and protestors, has produced a mismatch between the available UK power supply and the expected winter demand. The government has made strenuous efforts to patch up the gap between supply and demand: ageing nuclear power stations have been inspected and approved to continue for an extended life; polluting coal fired stations are being paid a premium to keep operating; deals have been struck with big energy users to alter their power use profiles, and switch off overnight at times of critical demand.

The National Grid says that 25 GW of power capacity has been lost from the system in the past year because of plant closures. Last winter the margin between peak demand and capacity was only 16 GW. So will the last minute deals cover the 9 GW shortfalls?

New technology will bridge the gap

New technology will provide the answer to the power gap, according to the UK government, which has been investing to encourage developments. Regrettably the pace of the development does not seem to have kept up with the expectation, in some areas.

Carbon Capture and Storage (CCS) systems will in theory reduce the carbon emissions from fossil fuel driven plants: the government has allocated £1 Bn to finance the commercialisation of such projects. One project is at Drax power station, the White Rose CCS project, which involves Alstom and BOC, plus a National Grid 75 km pipeline to deliver liquid CO2 to undersea storage caverns offshore. Drax Power itself is no longer investing in this CCS project: they will burn wood chips in some of the boilers at Drax, which are a renewable source – imported from the USA.

Another project financed under the Government scheme is on a CCGT gas-fired power station at Peterhead, in Scotland, where Shell and Scottish and Southern Electricity are the operators. Again the CO2 will be stored in depleted gas fields offshore.

In contrast, the incentives offered to UK home-owners with solar panels, for electricity delivered back to the grid, have been remarkably successful. The future commitment, over 20 years, has created a booming industry, and the government budget has been overspent – costs are £7 Bn this year. There is a significant growth in solar power generation – around 1,5% of total power, but maybe the sums were not done properly. So suddenly the scheme has been switched off, any new solar generation will only receive about 10% of the current rate. Solar cannot bridge the power gap on cold dark nights, though!

The sea provides the potential for green energy using either wave or tidal power. Research and prototype installations have been made in Portugal (providing 2,25 MW briefly in 2008) and in Australia (a buoy system, using water to drive turbines on-shore). In the UK, test and evaluation sites have been set up in the Orkneys and in Cornwall. The Scottish government set up a Pelamis based 3 MW wave farm in 2010, and more projects are being trialled. Wave power is seen as a viable technology for South Africa: the UK is volunteering to share its research along with China.

Dong Energy from Denmark has built two new offshore farms in the north of England. These give 8 MW from each 222 m tall turbine: a significant rise from the 3,6 MW 120 m units originally installed offshore – the costs per unit are not significantly higher for bigger columns. The latest developments come from Norway, where Sway Turbines has plans for a 10 MW turbine, with a 164 m diameter rotor and a 25 m open structure at the hub, which is part of the generator.

In the UK, with government funding, Blade Dynamics has developed an advanced design of wind turbine blade and tip, which can be assembled on site (https://www.youtube.com/watch?v=gz0IlPjU7Bc). A 78 m long example has recently been delivered to the government testing laboratories: Blade Dynamics was then acquired by GE, to join it with the recently acquired Alstom wind energy business.

Nuclear on the horizon?

Old technology is also on the rise, with the UK government guaranteeing a loan by the Chinese to the French owned EDF, which will build a new nuclear plant at Hinkley Point, for the UK. This is unlikely to produce any power before 2025, assuming the Areva reactor can be made to work: the two installed so far are not yet operating properly. The deal with China also involves the installation of two Chinese built reactors at sites near London, next to existing Westinghouse PWRs. The UK government pioneered and financed the first nuclear stations in the 1960s: now it seems to have turned its back on the possibilities and future potential of the new small modular reactor designs.

Nick Denbow spent 30 years as a UK-based process instrumentation marketing manager, and then changed sides – becoming a freelance editor and starting Processingtalk.com. Avoiding retirement, he published the INSIDER automation newsletter for five years, www.iainsider.com, and now acts as its EMEA editorial correspondent. His blog is on www.nickdenbow.com





Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

Buyout model for solar investment
News
Sustainable Power Solutions has introduced a buyout model that converts existing solar and battery systems into immediate capital for South African businesses.

Read more...
Innovation award for Beckhoff’s XTS machine
Beckhoff Automation News
The Premio Innovazione award has confirmed that Tetra Pak’s Cap Applicator 40 Speed Hyper has achieved a machine solution that pushes the boundaries of conventional packaging lines with a highly dynamic mechatronic solution based on XTS technology from Beckhoff.

Read more...
Vision meets reality at the Africa Automation Indaba
News
At the Africa Automation Indaba 2026, the panel ‘Automation for Africa – Opportunities, Challenges and Next Steps’ will feature a rare, high-level exchange where technology, ethics, entrepreneurship and data-driven reality shape what comes next for the continent.

Read more...
From the editor's desk: A tool not a crutch
Technews Publishing (SA Instrumentation & Control) News
Every year, the dictionaries try to summarise a year of human behaviour with a single word, the word of the year. You can question the value of this, but it’s quite entertaining. Words are important, ...

Read more...
Timken funds Kids Haven STEM classroom
News
A bright new chapter in digital education has begun at Kids Haven with the official opening of a fully equipped STEM classroom at the Kids Haven Village. This exciting addition was generously donated by Timken South Africa and expertly installed by Breadline Africa.

Read more...
Technology trends that will and won’t shape 2026
News
A whitepaper by ABI Research shows that a clear trend is taking shape, and 2026 is set to be characterised by practical, outcome-driven change.

Read more...
RS South Africa shapes future engineering talent
RS South Africa News
RS South Africa is demonstrating that nurturing future engineers goes beyond traditional classrooms or competitions. On STEM Day, the company shone a light on the full spectrum of its educational initiatives.

Read more...
ABB and Compu-Power bring high-efficiency UPS innovation to IS3 X-Change 2025
News
ABB recently participated in the 31st annual IS3X-Change 2025 in Cape Town, alongside its long-standing channel partner Compu-Power.

Read more...
UKZN’s SMART lab wins aviation award
News
: The SMART Lab at UKZN was awarded first place in the Aviation Research and Development category at the Civil Aviation Authority of South Africa’s award ceremony for outstanding contributions and achievements in the aviation sector.

Read more...
Meta and partners announce completion of 2Africa subsea cable system
News
Meta, in partnership with leading global and regional telecommunications companies, has announced the completion and activation of the core 2Africa subsea cable system. This marks a historic milestone in digital infrastructure, establishing what the world’s longest open-access subsea cable system.

Read more...









While every effort has been made to ensure the accuracy of the information contained herein, the publisher and its agents cannot be held responsible for any errors contained, or any loss incurred as a result. Articles published do not necessarily reflect the views of the publishers. The editor reserves the right to alter or cut copy. Articles submitted are deemed to have been cleared for publication. Advertisements and company contact details are published as provided by the advertiser. Technews Publishing (Pty) Ltd cannot be held responsible for the accuracy or veracity of supplied material.




© Technews Publishing (Pty) Ltd | All Rights Reserved