Electrical Power & Protection


Alwyn Rautenbach talks on solar power and the Assmang Khumani project

December 2013 Electrical Power & Protection

SA Instrumentation and Control speaks to Iritron’s managing director about photovoltaic solutions and their suitability for industrial projects in southern Africa.

Photovoltaic solar power in perspective

“The price of solar panels has come down over the last few years opening the door a little wider for certain renewable energy applications,” outlines Rautenbach at the beginning of our discussion on the viability of photovoltaic panels as an alternative energy source for industry. “But one must remember that the cost of a solar installation in an industrial project is also significantly influenced by tie-in into the grid, which can add significantly to the upfront costs. Looking purely at the solar panels with grid-tie inverters and structures, this cost probably ranges between R18 and R25 per kW. Working on R25, this means that for a 100 kW plant the equipment alone would cost about two and a half million rand.”

He stresses that this will almost double once the engineering and hidden costs associated with security, health and safety, mine specifications and foundation requirements are added. These have a significant effect on the ROI of the project, which is also influenced by whether the end-user decides to participate in the Eskom rebate programme or not. When all is said and done, it seems that a 100 kW photovoltaic installation will cost the customer about five million rand at today’s prices. The kicker of course, is that the future cost of fuel associated with this 100 kW goes to zero. Based on the current cost of electricity this gives an ROI of about three years, which is quite high, but after that the user essentially has the benefit of a free system. Of course, this depends heavily on the future price of electricity, which, it seems, is unlikely to drop anytime soon.

While there are many reasons that solar systems could be considered for applications in remote rural locations, Rautenbach believes one of the key drivers for industry is the pressure that Eskom is putting on mines and factories to improve their energy efficiency. In the case of a mine, the typical plant-wide efficiency initiatives that are undertaken do make the plant a lot more energy effective, but eventually it becomes a game of diminishing returns. This is where renewable sources like solar can make a difference, particularly to supply the energy required to power things like the office infrastructure and machines. “What you must remember though,” he cautions, “is that a 100 kW photovoltaic system requires almost one hectare of panels. What we really need is for the suppliers to get the efficiency up and the prices down; this is what will open up the application possibilities. I believe we will see this happening out of China in the future. Chinese manufacturers have the potential to dominate a market like this through their high volume low margin manufacturing approach. Of course this will take time and the quality must be there too, so for now, smaller systems are what we feel comfortable recommending to our industrial client base.

The renewable energy project at Assmang Khumani

About five years ago, Assmang Khumani approached Iritron to conduct a survey on the new Khumani plant to determine the overall efficiency of the mine, particularly how management could get closer to the commitment it had given to save energy. “Khumani is a relatively new operation, so built using the latest technology it is already energy optimal for the most part,” explains Rautenbach. “Initially, we bounced ideas around to see if Eskom will look at consumption across the entire Assmang operation. This with a view to being able to push production where it was needed and so compensate for operations that were down, say for maintenance. We gave this idea up after a few deadends that we reached, and so the final brief to Iritron remained to conduct the survey on the Khumani site in isolation.”

It’s a kind of magic

Literally translated, the brief to Iritron was ‘investigate the plant’s current electricity consumption and then make a proposal outlining where meaningful saving can be achieved’. One of the biggest challenges it faced was identifying a benchmark to use to judge the effectiveness of the solution it would ultimately propose – there simply was not another comparable local project at that time. “We were new to this in the market and knew we had to master the technology before we could contribute to the project,” says Rautenbach. “We had to start from basic principles and investigated various systems before we selected the technology that was eventually applied to this project.”

It was after Iritron met with a solar panel distributor in Miami that the penny finally dropped: it was possible for a manufacturer to meet most of its ancillary energy requirements using electricity generated from solar panels. “We always knew that once we could generate the electricity we would understand it,” states Rautenbach. “Now that we had identified our method, we could start looking for the specific areas we were going to electrify using our alternative power source.”

Here comes the sun

Air conditioning was identified as one of the biggest auxiliary consumers of electricity in this particular Assmang environment, office machines and PCs were identified as other examples of power hungry devices. Armed with its new knowledge about the viability of solar as a supply for basic office requirements – lighting, HVAC, kitchens, washing machines and hot water – the Iritron team recommended a 100 kW project to evaluate the effectiveness of the solar farm concept. “Our client was delighted,” says Rautenbach. “This is exactly what Assmang required to demonstrate its commitment to reduced dependence on grid-based electricity supply.” He estimates the saving for Assmang as 1 MW per day, but is reluctant to commit to a specific ROI due to confidentiality issues. He smiles though when we ask if two and a half years would be in the ballpark.

After the initial investment the ongoing operating costs are low, very little maintenance is required and this mainly involves cleaning, general electrical maintenance and ensuring the air conditioning in the inverter rooms is functioning properly – important to keep the power electronics cool in the high ambient temperatures found in the region. There are some interesting supply permutations though, for instance when the washing machines are not being used then the plant is over generating. This can also happen during spring and autumn when the demand for cooling (or heating) is less severe. “We considered the worst case though,” says Rautenbach. “We went for a 100 kW plant because once you consider efficiency then you no longer generate at the rated power, a 100 kW plant probably only gives about 90 kW on the grid.”

This of course raises the question of future expansion. Rautenbach says that this is not a problem with systems like the one at Assmang, because there is space available to house the extra solar panels that would be required, something other potential adopters of the technology would do well to remember.

The initial project took 14 months from inception to handover, but Iritron should be able to improve significantly on this with such a successful implementation under its belt. “We are going to be expanding our footprint further into the renewable energy market,” concludes Rautenbach. “The Northern Cape with its excess of sunshine has been identified for future solar projects and our experience there leaves us in an ideal position to compete for them.”

For more information contact Alwyn Rautenbach, Iritron, +27 (0)12 349 2919, [email protected], www.iritron.co.za



Credit(s)



Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

The climate change reality in South Africa: An engineer’s call to action
Electrical Power & Protection
This year’s World Engineering Day on 4 March was a powerful reminder of the critical role engineers play in driving progress toward the sustainable development goals.

Read more...
Empowering Africa’s renewable energy future
Electrical Power & Protection
As a global leader in renewable energy technology, SUNGROW has pioneered sustainable power solutions for over 28 years. At the recent Africa Energy Indaba 2025, SUNGROW showcased its advanced energy solutions designed to meet the diverse needs of the African continent.

Read more...
The role of electromechanical solutions in supporting Africa’s industrial growth
Electrical Power & Protection
Africa’s industries are transforming rapidly. Fuelled by a huge demand for energy connectivity, better infrastructure, increased manufacturing and responsible resource management, electromechanical solutions are key to shaping this growth, allowing industries to scale up their operations efficiently and sustainably.

Read more...
Empowering South Africa’s IPPs for a renewable future
Electrical Power & Protection
Many crucial parts of the economy of the future will be hugely energy intensive, foremost amongst which will be electrified transport and the large data processing required by automation and AI. Successful economies will be those that can ensure businesses and investors have access to a stable supply of low-cost renewable energy. South Africa has the opportunity to become a global leader in this regard.

Read more...
Sustainable mining operations escalate as demand for critical materials to double
Electrical Power & Protection
The mining sector is at the forefront of the energy transition due to its role in extracting essential materials and minerals necessary for green technologies. As demand for renewable energy, electric vehicles and other sustainable technologies increases exponentially, so will the demand for these necessary materials.

Read more...
Monitoring partial discharge on medium voltage switchgear
Schneider Electric South Africa Electrical Power & Protection
Schneider Electric South Africa has launched its EcoStruxure Service Plan (ESP) in the Anglophone African region for medium voltage (MV) switchgear

Read more...
Raptor switches
Phoenix Contact Electrical Power & Protection
The Phoenix Contact Raptor switches enable reliable and safe operation in extreme ambient conditions. The managed switch portfolio meets the stringent requirements of IEC 61850-3 and IEEE 1613 standards and is ideal for critical infrastructure and power supply applications.

Read more...
Electrical safety warning indicators
Electrical Power & Protection
Remlive electrical safety warning indicators have been keeping the workplace safe for more than 25 years.

Read more...
Self-contained standalone lightning warning system
Senseca Electrical Power & Protection
The BTD-200 lightning warning system from Biral (UK) is a complete detection and warning system. Its highly specialised aviation grade lightning detection technology delivers the warning as soon as lightning is detected and before the first strike.

Read more...
Half brick second generation converter
Vepac Electronics Electrical Power & Protection
The Supreme series half brick second generation converter from Vepac is composed of isolated, board-mountable, fixed switching frequency DC-DC converters that use synchronous rectification to achieve extremely high power conversion efficiency.

Read more...