Africa’s largest rotor pole ­refurbishment

July 2017 Electrical Power & Protection

In the largest repair of this nature in Africa, Marthinusen & Coutts recently refurbished 11 of the full set of 14 rotor poles of Motor Generator Unit Three at Eskom’s Ingula Pumped Storage Scheme on the Drakensberg escarpment. The rotor poles were extensively damaged during a fault condition at the station, and the return to service of the unit was of national importance.

Working closely with stakeholders, an extensive local programme of testing, dismantling, inspection and repair was conducted by Marthinusen & Coutts within extremely tight time-frames to accommodate the criticality of the project. A technical audit confirmed that facilities at the company’s 8000 m² main workshop in Cleveland, Johannesburg, and its 12 000 m² Power Generation division in Benoni, were up to the daunting task. All 14 main rotor poles were then collected from Ingula Pumped Storage Scheme and dispatched to the Benoni works. Each pole weighed 12 tons, with the coil alone weighing in at over two and a half tons.

It was vital that Marthinusen & Coutts determined not just the electrical status of the windings, but the health and physical integrity of each entire rotor pole (body and coil). They were therefore subjected to insulation resistance and inter-turn insulation tests, comprising both impulse and power frequency inter-turn insulation tests. Extensive visual inspections were also conducted. The test results were analysed, resulting in the decision to refurbish 11 of the 14 poles; two coils were accepted as healthy and the station owned a spare universal coil.

To facilitate the grinding procedure necessary to remove the support side brackets from the main rotor poles, a customised heavy duty jig was manufactured. After the severity of the damage was determined, various techniques and repair concepts were tabled and discussed in detail. It was finally agreed that the coils be stripped of their existing inter-turn insulation layers and the coils be reinsulated, heat cured using 2500 A, including pressing at up to 1000 tons, and re-assembled to the main poles. To fast track the process, Marthinusen & Coutts prepared custom parallel operations at the two facilities by separating the dirty and clean processes, with full clean conditions areas for the critical pressing and heat curing processes.

Manufacturing the tools and equipment for the work demanded substantial engineering and sourcing capacity. Among the items to be custom made were various tables and jigs to help move the coils in and out of the burn-out oven. A coil removal rig to remove coils safely from the main pole body was built, as well as two heavy duty consolidation rigs with a set of 1000 ton hydraulic jacks and their dedicated power control unit.

Marthinusen & Coutts also designed and constructed a dimensionally accurate dummy pole centre to help ensure correct fitment of coils to the main poles. Other items included a 2500 A direct current controlled rectifier to assist with the curing cycle, heavy duty turning rigs, lifting assemblies and a magnetic link for inter-turn insulation testing.

The scope of work included pyrolising the coil insulation in a controlled oven environment at 300°C and removing the existing insulation. The copper stacks were cleaned and polished, new insulation was pressed and prepared, and all new insulation kits were manufactured with pre-impregnated Aramid paper. All pole coils were reinsulated and thermo-electrically cured with a 1000 ton consolidation pressure, after which they were cleaned and tested.

Work on the main pole bodies included removing the existing insulation and checking and testing the copper damper winding and series connectors. Weld scars were cleaned and polished and new insulation kits were supplied and fitted. In the final assembly and test stage, Marthinusen & Coutts repaired the existing support brackets to as-new OEM specification and tested them to meet international standards. Coils were fitted to the rotor poles and the coils sealed onto the main poles. Finally the finished rotor poles with coils were tested, crated and transported back to Ingula by Marthinusen & Coutts. Unit 3 is now operating to full capacity. The entire project was carried out under extreme pressure, in record time, and according to all the OEM specifications and requirements for new rotor poles.

For more information contact Richard Botton, Marthinusen & Coutts, +27 (0)11 607 1700, [email protected], www.mandc.co.za





Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

Unpacking the technoeconomic case for cleaner power in wastewater plants
Schneider Electric South Africa Electrical Power & Protection
Behind every reliable wastewater plant is an electrical system exposed to the effects of harmonics, voltage distortion and overloaded networks caused by fleets of variable speed drives on pumps and aerators.Together, they steadily drive up maintenance demands and elevate the risk of failure.

Read more...
Energy strategy as a competitive advantage for African businesses
Electrical Power & Protection
Energy is no longer simply something that businesses consume. When managed effectively, it becomes a controllable asset that supports resilience and efficiency and sets the foundation for long-term competitiveness.

Read more...
World’s fastest 14 bit arbitrary waveform generator
Vepac Electronics Electrical Power & Protection
The ARB Rider AWG-700 from Vepac is the world’s fastest 14 bit arbitrary waveform generator, with a 20 GS/s real-time update rate and 14 bit vertical resolution.

Read more...
Transformers for mining house in Botswana
ACTOM Electrical Machines Electrical Power & Protection
LH Marthinusen is completing the manufacture of two 30 MVA transformers for a mining house in Botswana.

Read more...
DIN-rail power supplies for reliable and efficient AC/DC conversion
Conical Technologies Electrical Power & Protection
The Claf Power AD75-2BxxS series DIN-rail power supplies are designed for industrial automation, control systems and process environments.

Read more...
Rethinking power for Africa’s data centres
Schneider Electric South Africa Electrical Power & Protection
Africa’s digital economy is scaling faster than its power systems. If it wants resilient, competitive and sustainable data centres, the starting point must be a grid-to-chip architecture rather than a genset-first mentality.

Read more...
The growing decentralisation of power grids
Electrical Power & Protection
The decentralisation of power generation is changing how national grids function. For electrical engineers, several new challenges and opportunities are on the horizon.

Read more...
Custom mini substations for Zambian copper mine
Electrical Power & Protection
Recent orders to supply seventeen specially engineered mini substations for an underground copper mine in Zambia reinforces Trafo Power Solution’s track record in delivering customised electrical solutons for challenging environments.

Read more...
Unifying building information into a sea of insight
Schneider Electric South Africa Electrical Power & Protection
Facility managers realise that in order to gain the most from building automation, they can longer deploy and operate technologies in isolation. Modern, integrated building management solutions address this challenge by bringing data from multiple sources and dispersed locations like HVAC, lighting, access control, lifts, generators, field devices, energy and

Read more...
Smart power solutions for a low-carbon future
ABB South Africa Electrical Power & Protection
As the world marked Earth Day 2026, ABB is highlighting the role of low-voltage smart power solutions in improving energy efficiency, reducing emissions and enabling more sustainable infrastructure.

Read more...









While every effort has been made to ensure the accuracy of the information contained herein, the publisher and its agents cannot be held responsible for any errors contained, or any loss incurred as a result. Articles published do not necessarily reflect the views of the publishers. The editor reserves the right to alter or cut copy. Articles submitted are deemed to have been cleared for publication. Advertisements and company contact details are published as provided by the advertiser. Technews Publishing (Pty) Ltd cannot be held responsible for the accuracy or veracity of supplied material.




© Technews Publishing (Pty) Ltd | All Rights Reserved