WEG generating electricity at Windsor Castle

December 2014 Electrical Power & Protection

A project delivered by Southeast Power Engineering of the UK has seen a mini power station installed on the River Thames at Romney Weir to generate electricity using environment-friendly, water-driven Archimedes screw generators. The completed design features two WEG W22 premium efficiency IE3 generators being driven via a gearbox to produce the electricity which now powers Windsor Castle.

The WEG units are special products for this application in the sense that they are generators based on a WEG W22 motor. When the screws need to be restarted, electricity is used, and then as the speed increases, so the motor function changes over to that of a generator. The rotation of the screw is maintained by the water which, in turn, maintains the generator speed in order to produce the electricity.

The scheme is the brainchild of David Dechambeau, managing director of Southeast Power Engineering, who has overseen every step of the design and installation process. “In order to make this project sustainable, it was essential that we select the most efficient equipment for the construction of this power station. The design called for a reliable generator with superior efficiency ratings and on balance the WEG component definitely fitted the criteria and it was straightforward to install.”

The power station has been generating electricity since the middle of 2013 and is in the final stages of completing its testing and commissioning. It comprises two Archimedes screws manufactured by Landustrie, each weighing 40 tonnes, connected to the WEG generators, which are now delivering 320 kW/h at peak flow, exceeding the original design criteria.

The generators were designed and manufactured in Portugal at WEG’s dedicated European manufacturing site. They are rated at 185 kW and produce electricity at 400 V, which is then fed via a 500 kVA transformer to an underground line that connects to Windsor Castle and to the national grid.

Efficiency was a key target for this application as the installation has a fixed ROI period. At 96% efficiency, the WEG motor/generators represented one of the best investments Southeast Power could make to ensure the six-year ROI target was met. The installation has a minimum guaranteed design life of 50 years while Southeast Power has a 40 year tenancy of the site, which means that reliability and longevity were also very important considerations. If the screws stop turning, it means a direct consequence in terms of revenue.

“This was a very important project for us, not only because we are supplying the Royal Household, but also as an initial stepping stone for a number of similar projects. It is essential that we installed the most efficient and ecologically sound power plant as possible. The work we are completing now will help to deliver future projects using similar technology as demand for sustainable power increases,” concludes Dechambeau.

For more information contact Kirsten Larkan, Zest WEG Group, +27 (0)11 723 6000, [email protected], www.zest.co.za



Credit(s)



Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

Quantum battery charges in a quadrillionth of a second with a laser
Electrical Power & Protection
Researchers have created the world’s first miniature, proof-of-concept quantum battery. If the technology can be replicated, it could transform the field of energy storage forever and open up new possibilities for lightweight, remote electrification, experts say.

Read more...
Phoenix Contact brings machine learning forecasts ito energy management
Phoenix Contact Electrical Power & Protection
Phoenix Contact is extending its Energy Management Service to include a powerful forecasting function.

Read more...
Unpacking the technoeconomic case for cleaner power in wastewater plants
Schneider Electric South Africa Electrical Power & Protection
Behind every reliable wastewater plant is an electrical system exposed to the effects of harmonics, voltage distortion and overloaded networks caused by fleets of variable speed drives on pumps and aerators.Together, they steadily drive up maintenance demands and elevate the risk of failure.

Read more...
Next-generation oil-free motor systems with active magnetic bearings
WEG Africa Motion Control & Drives
WEG and SpinDrive are collaborating to integrate SpinDrive’s AMBs and built-in IoT condition monitoring into WEG’s market-leading electric motor offering, creating an oil-free, maintenance-free drive solution.

Read more...
Energy strategy as a competitive advantage for African businesses
Electrical Power & Protection
Energy is no longer simply something that businesses consume. When managed effectively, it becomes a controllable asset that supports resilience and efficiency and sets the foundation for long-term competitiveness.

Read more...
World’s fastest 14 bit arbitrary waveform generator
Vepac Electronics Electrical Power & Protection
The ARB Rider AWG-700 from Vepac is the world’s fastest 14 bit arbitrary waveform generator, with a 20 GS/s real-time update rate and 14 bit vertical resolution.

Read more...
Transformers for mining house in Botswana
ACTOM Electrical Machines Electrical Power & Protection
LH Marthinusen is completing the manufacture of two 30 MVA transformers for a mining house in Botswana.

Read more...
DIN-rail power supplies for reliable and efficient AC/DC conversion
Conical Technologies Electrical Power & Protection
The Claf Power AD75-2BxxS series DIN-rail power supplies are designed for industrial automation, control systems and process environments.

Read more...
Rethinking power for Africa’s data centres
Schneider Electric South Africa Electrical Power & Protection
Africa’s digital economy is scaling faster than its power systems. If it wants resilient, competitive and sustainable data centres, the starting point must be a grid-to-chip architecture rather than a genset-first mentality.

Read more...
The growing decentralisation of power grids
Electrical Power & Protection
The decentralisation of power generation is changing how national grids function. For electrical engineers, several new challenges and opportunities are on the horizon.

Read more...









While every effort has been made to ensure the accuracy of the information contained herein, the publisher and its agents cannot be held responsible for any errors contained, or any loss incurred as a result. Articles published do not necessarily reflect the views of the publishers. The editor reserves the right to alter or cut copy. Articles submitted are deemed to have been cleared for publication. Advertisements and company contact details are published as provided by the advertiser. Technews Publishing (Pty) Ltd cannot be held responsible for the accuracy or veracity of supplied material.