Coke drum integrity project at Canadian oil sands site

I&C February 2026 Motion Control & Drives

When it comes to equipment maintenance and facility shutdowns, particularly for the oil and gas sector, saving even a single day can result in significant cost reductions. Key to ensuring that a schedule is completed on time, or sometimes accelerated, is having the right planning, people and equipment in place. Mammoet supported a leading Canadian energy provider in Alberta’s oil sands with replacing its original eight coke drums at its base plant site in Fort McMurray. The project would extend the life of the original upgrader by 30 years.

The site upgraders use thermal and chemical processes, including coking and hydrotreating, to convert bitumen into synthetic crude oil. Coke drums gather the petroleum coke that is separated from the feedstock during the refining process. Weighing 270 tons a piece, each coke drum is 7,9 m in diameter and 29,8 m high. Moving them into place required one of the largest cranes in the world.

Through early involvement, Mammoet was able to advise on the right crane for the job, and when one of the new components was heavier than estimated, they fabricated specialised rigging for the lift. The team also helped accelerate the schedule by shortening the time between two of the biggest lifts of the project, helping enable the upgrader’s early return to operation.

Choosing the right tools for the job

Mammoet was brought in during the planning stages to conduct a feasibility analysis, assess which equipment would be best to remove the old drums, and get the new ones delivered to site and installed.

“In terms of the importance of the project and getting everything done within a specific timeline, this turnaround was completed safely, ahead of budget and schedule,” explains Kurt Reid, sales manager at Mammoet. “With the daily cost being significant, it was essential that planning happened years in advance”.

Mammoet was an integral part of the project for over seven years prior to execution, discussing the timing of lifts and movements. Its engineers undertook an entire crane review, assessing every suitable model in Mammoet’s fleet to select the right equipment. The biggest consideration wasn’t weight, but reach.

The engineering team first considered using an LR 11350 crawler crane placed beside an upgrader wall, but the option wasn’t feasible because it interfered with concurrent operations and maintenance work in the area. Mammoet’s PTC210DS ring crane was chosen for its ability to lift the six-drum derrick weighing over 1200 tons. Its long reach also allowed assembly away from other ongoing work. As the PTC had to be erected inside the coke pit, civil work was needed to strengthen the ground beneath it. Around 200 piles were driven into the ground to build a solid foundation.

Getting everything ready and in place

Prior to project execution, the new components were delivered to site. They were transported from their fabricator in Edmonton to Fort McMurray using prime movers on Alberta roads, and self-propelled modular transporters (SPMTs) on site.

This process started a year and a half before the project area would shut down for execution. Niek de Winter, corporate account manager at Mammoet, explains why. “Our plan was to ensure that all necessary equipment, materials, and components were delivered to the site by December of the previous year. This approach would allow the turnaround process to commence promptly and without delay upon the scheduled plant shutdown on 1 May.The crane was assembled, the coke drums and derricks were on site, everything was there months ahead of time. This allowed us to eliminate delays mid-project”.

On site, two sets of SPMTs and crews allowed things to move forward continuously and the PTC crane to be constantly fed.

Using the PTC to save time and cost

The old derricks were lifted first, followed by the eight coke drums and finally their concrete foundation sections. The old components were placed onto SPMTs and driven to a nearby laydown area for decommissioning. For the installation of the new components, the process then happened in reverse.

The fourth deck derrick ‘supermodules’ were transported to the facility in smaller modular sections and then moved and assembled on site. The base of these supermodules made up the operating deck of the coke drums and were assembled via SPMT from the smaller modules. The derricks were erected with Mammoet crawler cranes.

Due to a weight increase of the largest derrick supermodule, the project team at Mammoet had to maximise use of the PTC210 to deliver the needed lifting capacity. It was reconfigured with a double masthead kit, and specialised rigging was also fabricated.

Accelerating the schedule

Thanks to detailed planning, specialised equipment and the disciplined approach, production at the site could continue right up until 30 April, the day before the shutdown. From factory to foundation, Mammoet safely and efficiently managed its components on site ahead of the turnaround.

“As soon as we are called on, we are ready to perform the next lift. When you have a client that is planning their multi-week event right down to 15-minute intervals, time is of the essence,” concludes Reid.

For more information contact Jana Wolf, Mammoet, [email protected], www.mammoet.com




Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

Mammoet completes major bridge replacement at Amsterdam Centraal Station
Motion Control & Drives
Mammoet completes the second of five major bridge replacements at Amsterdam Centraal Station, transporting steel deck sections by water to keep the station open throughout the works.

Read more...
ndustry expertise drives SEW-EURODRIVE’s Electra Mining Africa presence
Motion Control & Drives
SEW-EURODRIVE will showcase industry-specific drive technology, modernisation services and expanded aftermarket support at Electra Mining Africa 2026, with a focus on lifecycle support and operational optimisation.

Read more...
Next-generation motor management solution
Schneider Electric South Africa Motion Control & Drives
Schneider Electric has launched its TeSys Tera motor management solution in the West African market, combining advanced motor protection, digital connectivity and real-time diagnostics for manufacturing, mining and water applications.

Read more...
Premium slewing rings from SKF
SKF South Africa Motion Control & Drives
SKF’s slewing bearing portfolio spans standard and customised designs across a wide range of types and sizes, backed by advanced monitoring, remanufacturing services and application engineering expertise for demanding industrial applications.

Read more...
World’s first fully electric hydrogen fuel cell aircraft engine
Motion Control & Drives
Airbus and MTU Aero Engines are establishing a joint venture to industrialise hydrogen-electric propulsion systems for commercial aviation, combining liquid hydrogen expertise with fuel cell development to support the ZEROe programme’s 2035 target.

Read more...
Monopile handling innovations boost offshore wind farm
Motion Control & Drives
Mammoet’s XXL monopile transport system and new MTC 1600 terminal crane are helping offshore wind developers safely marshal and install ever larger monopile foundations, as demonstrated on Van Oord’s Baltic Power project.

Read more...
Automation without the mega factory
Yaskawa Southern Africa Motion Control & Drives
Mid-sized South African manufacturers are turning to targeted, low-risk automation to solve specific bottlenecks rather than chasing full factory transformation, helped by retrofit-friendly robotics and advanced simulation software.

Read more...
Duplex worm gears for precision backlash adjustment
Motion Control & Drives
KHK USA has introduced duplex worm gears that allow precise backlash adjustment through simple axial movement of the worm shaft, eliminating the need for gearbox housing alterations during assembly or maintenance.

Read more...
Choosing the right level of protection in modern automation
Motion Control & Drives
Choosing the right ingress protection rating for a motor or drive is less about maximising the number, and more about understanding what the machine will actually face in operation.

Read more...
Osterwalder launches multi-plate, fully electric powder press
Motion Control & Drives
Osterwalder Technology has launched the MPneo 480, a 480 kN fully electric multi-plate powder press with up to six cross-pressing modules. Designed for hard metals, ceramics and advanced engineered materials, the press supports complex geometries and offers optional

Read more...









While every effort has been made to ensure the accuracy of the information contained herein, the publisher and its agents cannot be held responsible for any errors contained, or any loss incurred as a result. Articles published do not necessarily reflect the views of the publishers. The editor reserves the right to alter or cut copy. Articles submitted are deemed to have been cleared for publication. Advertisements and company contact details are published as provided by the advertiser. Technews Publishing (Pty) Ltd cannot be held responsible for the accuracy or veracity of supplied material.




© Technews Publishing (Pty) Ltd | All Rights Reserved