IT in Manufacturing


Digital revolution in transformer substations

February 2025 IT in Manufacturing

The energy sector is under a lot of pressure. Distribution grid operators need to get their infrastructure ready for the energy transition and fast. By 2030, some 80 percent of electricity is to be generated from renewable sources. A pilot project at naturenergie netze in Germany is demonstrating how transformer substations can be modernised more quickly. In collaboration with software suppliers Eplan and entegra, this southern German distribution grid operator is now working for the first time on a digital twin that will greatly speed up the planning and further development of transformer substations.

In the past, there was distribution. For decades, energy was simply distributed in one direction, from continuously operating coal and nuclear power stations to transformer substations, and from there to end consumers once the voltage had been stepped down several times. To use a road traffic analogy, this quiet one-way street has now become a busy city centre road network. Nowadays, the energy mix changes hourly with the wind and weather, so essentially there isn´t a reliable base load any more. Wind farm and solar system operators feed in energy decentrally at medium- and low-voltage levels, so power grids now work in two directions. Heat pumps and electric vehicle charging stations mean higher consumption, while familiar load profiles that peak in the early evening are now a thing of the past. However, both the quality of the supply and the 50 Hz frequency must be guaranteed at all times.

Grid operators are facing a mammoth task. They need to make their grids fit for these complex requirements. For naturenergie netze, this involves new construction work, as well as modernising a number of existing transformer substations. The plants need to be adapted to suit the increasing demand for electricity, but that isn´t the only challenge. A bigger challenge is that they need to be adapted to cope with a much higher level of flexibility in terms of energy sources and flows and the precise control of electricity.

A digital twin

naturenergie netze was quick to address these challenges and is currently working on a pilot project as it modernises one of its systems. The grid operator is using a digital concept to plan and configure its conversion of the Rheinfelden transformer substation. The new approach applies even to the preliminary work. Rainer Beck, a grid development coordinator, explains: “Before we start planning, we create a digital twin of the transformer substation. This is a virtual representation with all the data for both the live components (the primary technology) and the control level (the secondary technology) and, of course, for the buildings and all the peripherals. We then plan the conversion on the basis of this digital twin.”

Another reason why this is a challenging task is that the primary and secondary technologies are planned using different CAD software tools. In this pilot project, this issue was resolved by a very special collaboration. Among members of the VDE ETG ‘digital twins for electrical energy systems’ task force there were two leading suppliers, entegra with its primtech software solution for the primary technology and Eplan for the secondary technology. Both had prepared for precisely what naturenergie netze needed for the first planning stage, namely combining primary and secondary technology in a single model.

Major efficiency gains

For this unique project, entegra and Eplan were looking for an innovative distribution grid operator with a suitable pilot project to get involved as the third party in this collaboration. Contact with naturenergie netze came at exactly the right time, especially since the project in question was a complex one. As Beck explains: “The aim of the project is to renew all the secondary technology in an existing, highly complex transformer substation during ongoing operations. It´s easy to understand why involvement in this project was appealing. It would normally take two to three years to plan and implement the modernisation, but the new planning methodology will really speed things up. Everybody involved in the project agrees.”

Matthias Schuy, business development manager at entegra, explains: “What we´re doing here is integrating a transformer substation´s primary and secondary technology into one digital twin. This has never been done before, but promises major benefits.” Beck adds: “Ultimately, we need to prove that the one-off investment will pay off quickly. After the first project phase, the preliminary planning, we see considerable time savings during the actual conversion of the transformer substations. What´s more, this applies to every project.”

One model for all users

During the first stage of the project, the transformer substation was scanned, photos were taken of the rating plates, and the primary technology data generated was compared with the data from the asset management system. The result was a valid, functional primtech 3D model of the transformer substation. During a fully automated process, the datasets created in primtech were then exported to Eplan via an interface and used as the basis for planning the secondary technology in Eplan. Finally, the data from the secondary technology was integrated into the digital twin. By documenting the scenario as it currently stands, the basis has been provided for replacing the transformer substation´s secondary technology efficiently. “This is a really important step. All the data is verified. We basically follow the ´single source of truth´ principle. The data in the original systems is left untouched and linked to the digital twin. This prevents redundancies that could prove problematic in the future,” explains Jan Oliver Kammesheidt, global vertical market manager for Energy at Eplan.

In terms of the architecture of the combined data model, the parties involved have created a special infrastructure. “There´s no leading system. Instead, there are merely different perspectives of one and the same model. The digital twin opens a window to the systems, for example, from primtech to Eplan or SAP. The digital twin therefore fulfils one of its main functions, namely offering centralised access to all relevant information for the transformer substation,” Schuy explains.

Standardising secondary technology

This collaboration by the three parties − entegra, Eplan and the distribution grid operator − was made possible, or at least made easier, by a decision taken two years ago. That was when naturenergie netze started using the Eplan Electric P8 and Eplan Pro Panel software solutions to plan its secondary technology − its control technology. Simon Rümmele, the grid development project leader, was responsible for this. “With Eplan, we can drive forward the standardisation and more efficient engineering of the secondary technology, and also use end-to-end planning during the operation phase for preventive maintenance and overhauls,” he says.

Lessons from mechanical engineering

The project is demonstrating that users in the electricity industry are benefiting from experience and solutions from mechanical engineering. In that sector, one in which Eplan has been active for decades, standardisation and industrialisation of panel building and switchgear manufacturing equipment is firmly established. As regards this step for transformer substations, there is still a lot of catching up to do, but it has to happen. “Up until now, transformer substations have been planned on a case-by-case basis and built as one-offs. However, this makes it very difficult to judge the need for modernisation and new-builds that are arising as a result of the energy transition. The sector needs to standardise much more than it has in the past. We are providing support and are delighted to have found an innovative partner in naturenergie netze. With the joint digital twin for primary and secondary technology, we are speeding up the process considerably and making it more reliable, too,” Kammesheidt explains.

Strong partners for the conversion

Rümmele says this is precisely what naturenergie netze is setting out to achieve. “We want and need to digitalise more, because we believe this will open up opportunities and make things easier in the future. That´s why we´re trying out the latest technologies and planning further pilot projects at our transformer substation in Rheinfelden. What´s more, with Rittal, the sister company of Eplan, we also have a strong partner on board for converting the hardware, in other words all the enclosure technology,” he explains.

naturenergie netze has also been planning standardisation for some time now, and the joint digital twin created by entegra and Eplan will provide the basis for this, too. Rainer Beck says: “We can envisage using two standard concepts and buildings in the 110 kV range and creating variants on the basis of these. We´re also working on this with the main primary suppliers. This will cut down the amount of time and planning required. This is vital, because we´re going to be forced to adapt the majority of our transformer substations to comply with the new requirements. The digital twin and the preliminary work being carried out by entegra and Eplan will help us with this. Through partnership and collaboration, we are coming up with a genuine innovation that will help us develop our grids and make them fit for the future efficiently.”

However, it is not only naturenergie netze who will benefit from the project. Kammesheidt concludes: “In contrast to the mechanical engineering sector, grid operators openly share information, because they´re not competing with each other. There´s already a lot of interest. I´m convinced that many grid operators can take what we´re doing here and in the VDE task force to plan and implement their conversion and new-build projects faster.”


Credit(s)



Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

Optimising the product design process
Siemens South Africa IT in Manufacturing
OPmobility is partnering with Siemens to adopt its Teamcenter X Product Lifecycle Management software. OPmobility’s increasingly complex products now include electronics and software, to create energy storage systems, which include battery and hydrogen electrification solutions and fuel tanks.

Read more...
Smart milling for resilient, sustainable food production
IT in Manufacturing
As the global demand for food continues to rise due to increasing urbanisation, the milling industry faces the challenge of balancing efficiency with sustainability. Bühler is committed to making milling more energy-efficient while maintaining high operational performance. Its solutions allow mills to reduce energy costs and ensure long-term sustainability.

Read more...
The evolving landscape of data centres in the age of AI
Schneider Electric South Africa IT in Manufacturing
The data centre industry is undergoing a period of rapid transformation, driven primarily by the explosive growth of AI. It’s clear that the demands of AI are reshaping the very foundations of data infrastructure. This isn’t merely about incremental upgrades; it’s a fundamental shift in how we design, power and operate these critical facilities.

Read more...
SA Food Review
IT in Manufacturing
Food Review is a monthly trade journal for South Africa’s food and beverage manufacturing industry, for industry professionals seeking detailed information on trends, technologies, best practices and innovations.

Read more...
Keeping an eye on oil consumption with moneo
ifm - South Africa IT in Manufacturing
Manufacturing companies in the metal industry need oils and other fluids that are consumed by their machines. To make this consumption transparent and to establish a link to the ERP system, Arnold Umformtechnik relies on the IIoT platform, moneo, in combination with the SAP-based software solution Shop Floor Integration (SFI) – both from ifm.

Read more...
AI accelerates energy transformation
RJ Connect IT in Manufacturing
With the rapid expansion of generative AI applications, data centre power demand is reaching unprecedented levels.

Read more...
Revolutionising mining operations with MineOptimize
IT in Manufacturing
Now more than ever, mining and mineral processing companies need to boost productivity, ensure safety, and protect the environment. ABB’s comprehensive electrification, automation and digital solutions portfolio is ideally positioned to meet these challenges across all mining processes, from mine to port, transforming performance in a digital world.

Read more...
Buildings in Africa’s urban evolution
Schneider Electric South Africa IT in Manufacturing
Africa is now an urban continent. How does the continent mobilise to accommodate urban dwellers and maintain and implement critical infrastructure that allows for this expansion? Building management systems provide a tangible solution to optimise resource use, lower operations costs and ultimately contribute to a growing continent that also employs green practices.

Read more...
TwinCAT Vision functionality extended
Beckhoff Automation IT in Manufacturing
The image processing and camera integration capabilities of Beckhoff’s TwinCAT 3 Vision software have been expanded.

Read more...
Automation software to future-proof your operations
Adroit Technologies IT in Manufacturing
As the official partner of Mitsubishi Electric Factory Automation, Adroit Technologies empowers businesses with cutting-edge solutions that reduce costs, improve quality and increase productivity.

Read more...