Giant transformers delivered in record time

October 2001 News

ABB supplied power transformers in record time to limit the consequences of the energy crisis in Brazil Electricity for 3,2 million people in the São Paulo region. ABB, the global technology group, supplied two extra-high-voltage (765 kV) power transformers to the Brazilian Utility Furnas - the period between the placing of the order and the delivery was just six months. Normally, delivery periods of over a year are quoted for products of this level of complexity. The two transformers allow the additional transmission of 1500 MW of electricity from the world's largest hydro power plant, Itaipu, to the region of Brazil around São Paulo. This is enough power to supply to 3,2 million people.

Brazil is currently undergoing a serious energy crisis. The volume of energy available cannot keep up with the fast rising need for power; on the contrary - the Brazilian government has already been forced to limit the consumption of power by law. Electricity has been rationed in Brazil since June 2001, and the low production capacities of the power plants can only be expanded very gradually.

In order to counter the threat of a blackout, the Brazilian power companies depend on reliable technology for the transmission of power. "Above all, we are proud that we were able to help our customer so quickly with the right technical solution," says Peter Smits, Head of the ABB Division Power Technology Products, "because every day of the energy shortage reduces the productivity of industry and restricts the quality of life of the people," he continued.

The two power transformers are now a part of the Tijuco Preto substation. Each unit has a rated power of 550 MVA and voltage of 765 kV. The extra-high-voltage transformers, which weigh around 280 tonnes each, were produced in ABB's Guarulhos factory. They are the largest transformers ever produced by ABB in Brazil.

A team of 35 engineers and fitters worked around the clock on the products for about six months. "During this time, our Brazilian colleagues were able to access the wide-ranging expertise of our worldwide technology and production network," says Joakim Olsson, who is responsible at ABB for power transformers. "The unusually short production time was only possible because of the very efficient planning and design process and the smooth teamwork with the customer." The ABB engineers saved more time by using a special transport concept (taking three instead of 30 days) and an innovative installation process on site (13 instead of 40 days).

ABB South Africa

(011) 236 7000

[email protected]

www.abb.com



Credit(s)



Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

Hitachi Energy ramps up global and African investments
News
Hitachi Energy ramps up global and African investments to support grid readiness for the AI era.

Read more...
Experience ICRA 2026 right here in Gqeberha, South Africa
News
The IEEE International Conference on Robotics and Automation (ICRA) is the largest robotics, automation, artificial intelligence, and manufacturing conference in the world. You can experience the premier keynote and plenary presentations in Gqeberha.

Read more...
What to expect at Africa Automation Indaba 2026: From AI readiness to bankable automation projects
RX Africa News
Africa Automation Indaba 2026 will give delegates a practical view of what it takes to move automation from ambition to implementation with a two-day programme focused on industrial readiness, skills development, policy alignment, investment realities and the future of intelligent operations.

Read more...
SKF achieves SaiMechE CPD accreditation
SKF South Africa News
SKF South Africa has achieved SaiMechE CPD accreditation, a decisive step that empowers the next generation of engineers.

Read more...
Elevating artisanal skills is key to revitalising South Africa’s economy
ACTOM Electrical Machines News
We need to challenge the stigma attached to artisanal and technical careers, and we also need a mindset shift supported by the schooling system so that young people understand future career pathways, choose subjects accordingly, and recognise that artisanal and technical skills carry equal value in a modern economy.

Read more...
One visit, five shows: practical solutions for safer, smarter operations
News
Five co-located shows will bring together the full picture of how organisations manage risk, compliance, infrastructure and energy.

Read more...
Smart power solutions for a low-carbon future
ABB South Africa Electrical Power & Protection
As the world marked Earth Day 2026, ABB is highlighting the role of low-voltage smart power solutions in improving energy efficiency, reducing emissions and enabling more sustainable infrastructure.

Read more...
From the editor's desk: A little bit of magic
Technews Publishing (SA Instrumentation & Control) News
Whatever your view is of America today, the Artemis II mission showed the world that it can still deliver moments of wonder. For a few days, the chaotic headlines gave way to something more. Who could ...

Read more...
Electra Mining Africa 2026
News
Electra Mining Africa will take place at Nasrec, Johannesburg from 7 to 11 September 2026.

Read more...
Woman of Stature Awards South Africa
News
In a powerful recognition of excellence in a traditionally male-dominated industry, Thabisile Phumo won the Woman in Mining and Engineering award at the 2026 Woman of Stature Awards South Africa.

Read more...









While every effort has been made to ensure the accuracy of the information contained herein, the publisher and its agents cannot be held responsible for any errors contained, or any loss incurred as a result. Articles published do not necessarily reflect the views of the publishers. The editor reserves the right to alter or cut copy. Articles submitted are deemed to have been cleared for publication. Advertisements and company contact details are published as provided by the advertiser. Technews Publishing (Pty) Ltd cannot be held responsible for the accuracy or veracity of supplied material.




© Technews Publishing (Pty) Ltd | All Rights Reserved