PLCs, DCSs & Controllers


DCS project on track

June 2010 PLCs, DCSs & Controllers

Yokogawa working together with Chevron in Cape Town.

Chevron began marketing product in South Africa in 1911. It now markets products here under the Caltex brand, which began as a partnership between Chevron and Texaco in 1936. The 100 000 barrel-per-day Cape Town refinery produces gasoline, diesel, jet fuel, LPG and asphalt. Chevron South Africa recently initiated a project to replace the existing Centum XL control system at the Cape Town Refinery with Yokogawa’s CS3000 FIO hardware and upgrade the control network to Vnet/IP.

Project background

The basis for the project is to ensure the refinery’s DCS (distributed control system) retains high reliability and the required availability. The risk of availability of the current control system is increasing due to its age which could result in increased maintenance costs and unplanned plant shutdowns or production losses. The intent is to replace the existing Centum XL control stations that have been in service in excess of 15 years with the latest Yokogawa CS3000 hardware and upgrade the control network to a faster and more efficient VNet/IP.

In June 2008 Yokogawa SA was appointed as the principal contractor with overall responsibility for the project. Ilitha was appointed as sub-contractor for the design and installation with the installation being awarded to RSI. Chevron appointed Phillip Venter as its project manager with the Yokogawa project manager reporting directly to him.

Project summary

The main objective is to upgrade the control system live, which requires hot cutovers during the switchover from the old to the new system. This ensures there is no downtime on the plant and that all instruments and controls can be tested immediately after the cutover. Structured and formal project management and engineering procedures were developed and are being followed to ensure all the process requirements are implemented and all the risks are mitigated. The execution procedure culminates in a thorough risk assessment process involving all the key stakeholders.

Reliability, maintenance, advanced control, construction and operations representatives have all been assigned to the project to ensure every Chevron requirement is met. Prior to the hot cutover of each control station the current program is re-configured for the CS3000. A formal process is followed to ensure all the control logic and functionality is retained and complies with the software configuration standard.

After the approval of the design, the Yokogawa CS3000 hardware is installed into the DCS panels and they are acceptance tested. The hot cutover process does not interrupt the continuous operation of the plant and is carried out on an individual I/O point basis. To achieve this, the field wiring is transferred from the old DCS to the new and at the same time the existing configuration (program) is disabled and the new configuration activated. To ensure there is no disruption to the plant, control valves need to be bypassed until they are successfully cutover.

Key success factors

Project manager Phillip Venter says: “There are several factors that I believe are major contributors to the ongoing success of this project. From the RFQ stage of the project there has been excellent teamwork between Yokogawa and Chevron, we shared the vision of successfully completing the project within schedule and budget, with no production loss and zero incidents.

“Having the entire Yokogawa team in one location on site has drastically improved the efficiency of the team. This, coupled with each team member’s personal commitment to the project has made it a pleasure to work with Yokogawa.”

Statistics to date (April 2010)

* Overall project progress – 78% complete.

* 16 out of 24 FCSs cutover – 67% complete.

* 4520 of 7118 I/O cutover – 64% complete.

* 20 out of 24 FCSs installed – 83% complete.

* Incident free man-hours on site – 35 050.

* Project within budget and scheduled for completion in Jan 2011.

For more information contact Charles van Haght, Yokogawa South Africa, +27 (0)11 831 6300, [email protected], www.yokogawa.com/za



Credit(s)



Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

All eyes on the modern DCS platform
Schneider Electric South Africa PLCs, DCSs & Controllers
Modernised DCS platforms are no longer confined to hardware-dependent architectures. These systems have evolved to combine the strengths of both PLCs and DCS while adding capabilities that make them more open, resilient and collaborative.

Read more...
Automation solution for waste management at incineration facility
PLCs, DCSs & Controllers
Valmet is to deliver an automation system to Seongnam City’s incineration facility currently under construction in South Korea. By leveraging intelligent automation, the plant will optimise energy production, minimise emissions and deliver efficient, consistent performance throughout its entire lifecycle.

Read more...
Valmet’s supplies DCS to Europe’s largest electric boiler plant
Valmet South Africa PLCs, DCSs & Controllers
Valmet will supply an automation system to Helen’s Hanasaari electric boiler plant and a thermal accumulator being built in Helsinki, Finland. Once completed, it will be Europe’s largest electric boiler plant.

Read more...
Technology blueprint paves way for e-methanol fuel expansion
Schneider Electric South Africa PLCs, DCSs & Controllers
Schneider Electric has delivered the technology stack behind European Energy’s Kassø Power-to-Xfacility, the world’s first commercially viable e-methanol plant.

Read more...
PCS Global delivers turnkey MCC installation in Botswana
PCS Global Editor's Choice PLCs, DCSs & Controllers
PCS Global is delivering a turnkey containerised MCC installation for a major copper mining operation in Northwest Botswana.

Read more...
New energy-efficient evaporation line for dissolving pulp production
Valmet South Africa PLCs, DCSs & Controllers
Valmet will deliver a new evaporation line to Altri Biotek mill in Portugal. This delivery is part of Altri’s €75 million project to convert the Biotek mill to produce dissolving pulp for the textile industry.

Read more...
Valmet modernises turbine automation
Valmet South Africa PLCs, DCSs & Controllers
Valmet has received an order to deliver a comprehensive replacement of plant DCS and turbine control systems at Ennatuurlijk’s combined cycle power plant in the Netherlands.

Read more...
Hybrid DCS for an evolving industrial landscape
Schneider Electric South Africa PLCs, DCSs & Controllers
Today’s industrial automation continues to evolve at a blistering speed, which means traditional DCSs have to keep up to ensure continuous integration into modern, digital infrastructure.

Read more...
IIoT controller for the field and control cabinet
ifm - South Africa PLCs, DCSs & Controllers
The IIoT controller from ifm is a powerful, communicative and flexible PLC solution in machine and plant digitalisation.

Read more...
Bringing the benefits of Ethernet to hazardous industrial environments
ABB South Africa PLCs, DCSs & Controllers
Christian Johansson, global product manager for ABB Process Automation explains how Ethernet-APL lets plant owners unlock more value from their process data, optimise performance and promote safer operations.

Read more...









While every effort has been made to ensure the accuracy of the information contained herein, the publisher and its agents cannot be held responsible for any errors contained, or any loss incurred as a result. Articles published do not necessarily reflect the views of the publishers. The editor reserves the right to alter or cut copy. Articles submitted are deemed to have been cleared for publication. Advertisements and company contact details are published as provided by the advertiser. Technews Publishing (Pty) Ltd cannot be held responsible for the accuracy or veracity of supplied material.




© Technews Publishing (Pty) Ltd | All Rights Reserved