SCADA/HMI


Radical information management overhaul at SA Mint

August 2015 SCADA/HMI

Struggling with a manufacturing information management system that was installed in 1992 and last updated in 2000, SA Mint decided that it was time for a radical upgrade that would involve the latest MES and EMI technologies and approaches commensurate with the company’s product excellence and world-wide reputation.

The manufacturing process at SA Mint is characterised by a need for efficiency, security and tight production accounting – not to mention consistent product quality and dependable automation. The company bears a unique responsibility for delivering high quality products consistently, on time and in large volumes. This is an environment that has little or no tolerance for unreliable performance or lack of control and which has to meet the budget constraints of 21st century economics.

The production process is quite complex and has a large number of steps that must be followed precisely to make a single coin but, although this was already being handled, the real problem lay with management information – there wasn’t any. This meant that business continuity management couldn’t be guaranteed and reporting was a tedious business which was seldom on time to be effective.

Other concerns were that the existing solution couldn’t be integrated with others, depended on only one person for support and was based on very old operating and database management systems as well as an ancient technology infrastructure that was no longer supported.

“A decision was made to completely overhaul and enhance our factory systems,” says Lungile Binza, CIO at the South African Mint Company. “This was the start of project Pelo, a Sesotho word for heart, as this would be the heart of our operations. The plant needed a system that would provide material traceability, ensure data integrity and provide a solution flexible enough to accommodate changes in our manufacturing environment. The system would also have to assist with inventory optimisation by providing information about the availability and location of inventory items. We were looking forward to far greater visibility into our KPIs while the system facilitated production flow without compromising control or security at the same time as providing real-time production information including OEE.”

After a false start, project Pelo was put back on track based on SA Mint’s business needs rather than the process requirements. “At the time of this restart, the MES workflow technology was brand new and there were no referral sites in South Africa. We knew that we couldn’t tolerate anything going wrong and adopting this technology was initially considered too risky and the proposals were rejected. We were not going to have a guinea-pig experience,” continues Binza. “But a top-level presentation by Wonderware showed us their commitment to a future where model-driven MES and workflow management would become the norm because that’s what customers wanted. This new paradigm would be introduced, supported and training would be provided just as had happened with the rest of Wonderware’s product range. In fact, because of the needed human interaction and decision-making at the MES level, it soon became apparent that the integration of workflows would become the norm rather than the exception. Even so, the board of SA Mint insisted on introducing a system of checks and balances - but more about that later.”

Implementation

In 2012, Pelo phase 3 was started and the first step was to address the needs of the plating area where business objectives included:

Allowing the business to schedule any denomination through the plating area at any time.

• Assisting the production team with the on-time delivery of products through planning methodologies such as theory of constraints (ToC) and lean manufacturing practices.

• Manufacturing good quality products.

• Providing production management the information to reduce manufacturing costs.

• Replacing the current factory and material handling systems.

• Interfacing with other systems such as the ERP and material handling systems.

Next in line were the plating area’s operational requirements:

Promoting the flow of material through in-line processing.

• Improving the traceability of the material by ensuring that, in case of a breakdown of the upstream equipment, there is off-loading capacity of the work in process at both the QA stations and the furnace exit.

• Eliminating storing material on the shop floor.

• Minimising manual movement of the material in and out of the line and across the plating lines (i.e. furnace and polishing).

• Creating customer value and continually reducing waste.

• Embedding 5S principles and improving housekeeping.

SA Mint selected system integrator, Systems Anywhere Coastal to assist with the implementation because of the company’s track record of successfully supplying multi-level decision support solutions to many companies in the mining and manufacturing industries. “We needed to track production, downtimes, shifts and running times as well as monitor the status of machine and production weights,” says Systems Anywhere Coastal software engineer, Paut Kotze. “All development had to comply with SA Mint’s standards and quality criteria and this was especially important in the case of validating manual entries through the 14 InTouch HMI stations. These display production input, output and stoppages in real time. We also developed our own security features for linking to other systems.”

Wonderware’s System Platform, host to all applications including the model-driven MES and business intelligence solutions, provided easier system maintenance and the management of standards through its centralised Integrated Development Environment. “By providing a single source for software management, the definition, deployment and maintenance of standards as well as the integration of third-party solutions, System Platform justified its reputation as industry’s operating system,” says Kotze.

System development took about three months, with a further two months of extremely thorough integration testing. Commissioning took two weeks and another two weeks was spent monitoring the interaction between the operators and the system. This was followed by two months of factory acceptance testing and finally a two-month stabilisation period.

Wonderware Skelta BPM is central to the implementation because it manages the workflow between people. It could be considered as process control at the human level. “No longer did we have to write multiple scripts in order to check if something had been done,” says Binza. “The application gave us drag-and-drop simplicity so that we could easily develop and maintain workflows while referencing various databases as well as the scada systems. It helped us enforce business rules and standards as well as traceability of users and production.” The Enterprise Manufacturing Intelligence (EMI) aspect of the project is not only helping SA Mint collate valuable decision and management support information but also provides access to the areas of mobile reporting, analysis and control as well as cloud computing and the ability to make sense out of big data. The next challenge for SA Mint is the design and implementation of phase 4 which will include the final products area.

But had it all been worthwhile? Had the project provided SA Mint with real business benefits? On acceptance of this project, the board and steering committee of SA Mint insisted on verifiable checks and balances and appointed an independent auditing company to verify any business benefits the mint had realised through this exercise. The findings showed the following benefits:

Enhanced production, performance reporting and the realisation of business goals.

• Easy enhancements and the flexibility to cope with changes in the manufacturing environment.

• Accurate reporting of up and down times (data integrity).

• OEE reporting to help optimise plant availability and performance.

• Inventory optimisation though the availability and location of inventory items.

• Real-time production information measured per line and per machine.

• Limited manual reporting.

• Ease of integration with other systems, especially with the ERP system.

The proven effectiveness of modern process control principles on the shop floor has been applied to driving collaboration across people, processes and systems by streamlining workflow, enforcing business rules and monitoring the responses of responsible parties. Embedding workflow software within the production environment enables SA Mint to implement standard operating procedures and corrective actions by structuring repeatable, managed responses to process exceptions across the enterprise. This can be especially effective for processes and workflows that cross organisational boundaries such as operations, maintenance, laboratories and other business domains.





Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

HMI with maximum performance in the smallest of spaces
ifm - South Africa SCADA/HMI
Whenever clear communication, precision and performance in the smallest of spaces are required, the most compact member of ifm’s ecomatDisplay family is the perfect choice. The 11 cm HMI makes no compromises when it comes to human-machine interaction.

Read more...
Real-time data acquisition and reporting
Adroit Technologies SCADA/HMI
As the authorised distributor for Mitsubishi Electric’s Factory Automation, Adroit Technologies provides a range of factory automation products that include scada, PLCs, drives, HMIs and robots. Together, ...

Read more...
Upgrading your control system? Avoid these myths and misconceptions
Iritron SCADA/HMI
An upgraded control system has many benefits. However, the industry is plagued with control system upgrade myths and misconceptions. We explore the most common misconceptions and provide recommendations for mitigation.

Read more...
Display for controlling mobile machines
ifm - South Africa SCADA/HMI
The new ecomatDisplay dialogue modules from ifm have been developed for use in cabins and outside vehicles.

Read more...
Scada systems essential for smart, sustainable water sector
ABB South Africa SCADA/HMI
Uptake is hampered by a lack of project funding and slow implementation. Only when plants are automated can responsible water use be implemented effectively.

Read more...
Circular TFT displays with rotary switch
SCADA/HMI
The display sizes available are 1,3-inch, 2,1-inch, and 2,47-inch, making them ideal for applications such as heating systems, industrial controls, IoT devices and boilers, among others.

Read more...
Intuitive visualisation for the digital age
Emerson Automation Solutions SCADA/HMI
Emerson’s new PACSystems RXi HMI delivers intuitive graphics, smartphone-like usability, collaboration from anywhere and industrial ruggedness.

Read more...
Visualisation system sets new standards
Siemens South Africa Editor's Choice SCADA/HMI
The combination of Simatic HMI Unified Comfort Panels with WinCC Unified software, augmented with open APIs and option packages, delivers a fully scalable system for operator control and monitoring.

Read more...
Move over scada – New OIT/HMI systems provide increased choice
Omniflex Remote Monitoring Specialists SCADA/HMI
Omniflex’s EasyView range of HMIs can communicate with a variety of PLC and PAC hardware, and provides engineers with a flexible system to manage plant operations.

Read more...
Why telemetry should form a critical part of your water management systems
Schneider Electric South Africa SCADA/HMI
A complete, integrated sensor-to-enterprise solution can help utilities and operations to manage and run secure and reliable water infrastructure.

Read more...