System Integration & Control Systems Design


Successful control system cutover at Saudi Aramco processing plant

July 2016 System Integration & Control Systems Design

As Saudi Aramco’s largest oil processing facility and the largest crude oil stabilisation plant in the world, Abqaiq plays a pivotal role in its day-to-day operations. Abqaiq is the main oil processing centre for Arabian Extra Light (AXL) and Arabian Light (AL) crude oils and produces natural gas liquids (NGL) as a bi-product for Saudi Aramco’s daily oil processing activities. To support both the oil and gas operations, Abqaiq Plants produces its own electrical power, steam, instrument air and water.

For a complex of this size, an involuntary shutdown would mean great losses in production, which would negatively affect the company. In 2008, Abqaiq Plants team recognised potential challenges were on the horizon. Plants existing automation systems would experience obsolescence for distributed control system (DCS) controllers and emergency shutdown (ESD) processors and cards. In addition, these systems would no longer have technical support or training.

After some studies, it was determined that an upgrade and migration cutover of the plants automation system was needed. Abqaiq Plants team began to plan the process of upgrading the existing Emerson Provox DCS, Triplex Regent ESD systems, and burner management systems to the latest release of Emerson’s DeltaV DCS, SIS and BMS.

The team began the project towards the end of 2011 with a planned completion date of November, 2015. Although on-budget and on-schedule cutovers at a processing plant of this size do not happen often, the project team completed the cutover activities two months ahead of schedule.

Large complex plans for a hot cutover

Abqaiq Plants complex has three main divisions: oil, NGL and utilities, which are operated from three control rooms: North (north oil plants), South (south oil and NGL plants), and the UCR (utilities plants). The three control rooms interconnect with several process interface buildings (PIBs) to monitor and control plant processes. The control rooms and PIBs represent the veins of all Abqaiq operations and consist of several networks and risk areas.

Distributed over 20 locations, the project included upgrades to 325 controllers, 105 workstations, and 42 network devices. The team divided the project into four upgrade phases: north oil plants, south oil plants, NGL plants, and utilities plants.

Success meant not having a single interruption to plant operations, and the team had to minimise the shutdown time for some of the risk areas that have tight operations. Consequently, a hot cutover approach was chosen.

The team capitalised on three factors to overcome challenges and complete the project successfully with zero operation impact: human resource development, efficient testing procedures, and streamlined technologies.

Human resource development

Before starting the project, Abqaiq Plants management took proactive steps to develop a qualified team that included a mix of experienced and new personnel across project disciplines including automation, process, electrical and communication.

Several engineers, technicians, and operators were sent on vendor courses to increase their knowledge of the new systems. In addition, the project team simulated new systems process and operation scenarios in Abqaiq’s advanced technology centre. The simulation helped to ensure new systems readiness and familiarised plants engineers and technicians with them.

The team participated in several project activities and tests including factory acceptance tests (FAT) which increased the competency level of all team members.

Test procedures

To assure readiness and correctness of the new system and to achieve a smooth cutover, Abqaiq Plants’ engineering and operation teams developed testing procedures.

Detailed cutover sequence and contingency plan documents were designed to manage cutover critical activities and predict all possible scenarios during cutover and restoration procedures. The team also developed a plan to relocate the old DCS to a temporary cabinet and keep it running to control the plant. This approach helped to optimise the shutdown period for critical risk areas such as AXL shippers and steam production plants from one week to two hours. It also enabled a fast fallback strategy to the old system, in case of new systems failure.

Streamlined technologies

The project team took advantage of the upgrade to implement current technologies in the system network, monitoring and security areas. These simplified the cutover, project execution and troubleshooting.

For example, zoning and subnets were used to segregate the different control rooms’ networks. This segregation of networks and systems into unique areas enhanced system security. It also helped to isolate traffic and errors for easier issue tracing and network troubleshooting. In addition, a centralised management system was used to collect system events and key performance indicators.

Abqaiq Plants team came up with an innovative design to enhance the cutover period of some plant networks through installing a parallel connection between the old and new system networks. This innovative idea enabled the team to test the new system while maintaining old system connections. This method decreased plant downtime period from a potential 72 hours to zero and allowed for better system testing and recovery. In addition, to stabilise the plant sooner on the new system, critical loops were tuned with the help of Emerson consultants.

The project team also implemented a centralised patch management system to install security patches and antivirus updates. The centralised patch management system enabled the use of Guardian Support, which provided Emerson technology connections, and ensured the team would discover system issues if any arose. Not only did it help to mitigate Abqaiq system security and patch issues, but it also provided the team insights into what had Emerson learned from projects at other sites.

Business results and lessons

By combining planning with methods and technology, the project finished ahead of schedule and under budget. The resulting reduction in man-hours cut costs and gave the team more time to observe the new system and close some exception items.

Saudi Aramco employees, Emerson engineers, and contractors worked together collaboratively with support of Abqaiq Plant management as one team to achieve the goals of the project safely and with not even a single negative impact on production.

In addition, the young plant employees have been empowered to lead critical activities. The education and resulting confidence delivered several innovations and noticeable cost avoidances. In essence, Abqaiq Plants management capitalised on the development of people to ensure present project success and prepare for future system support.

In the future, Abqaiq Plants will plan to upgrade Provox IO cards to those of the DeltaV system. In addition the plant team will work to enable several enhanced DeltaV features such as Advanced Process Control (APC).

For more information contact Rob Smith, Emerson Automation Solutions, +27 (0)11 451 3700, [email protected], www.emersonprocess.com/mea



Credit(s)



Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

Compact valve position indicator
Emerson Automation Solutions Valves, Actuators & Pump Control
Emerson’s new TopWorx DVR Switchbox is an entry-level addition to the DV Series of valve position indicators. It combines a durable resin enclosure, compact size, and a patented cam design that provides a reliable valve position feedback for water and wastewater systems, food and beverage production lines, and industrial utilities.

Read more...
Understanding the role of AI in generative engineering design
System Integration & Control Systems Design
When a design engineer sets out to design a new part, component, or assembly, the intent is to meet the design requirements for fit, form and function, and also incorporate a certain degree of innovation and elegance to the overall design. There is no reason to re-invent the wheel by introducing a new design.

Read more...
Ultra-compact mass flow meters with advanced transmitters
Emerson Automation Solutions Flow Measurement & Control
Emerson has introduced the Micro Motion G-Series line of Coriolis mass flow and density meters, the most compact dual-tube Coriolis mass flow meters on the market. They offer the same level of quality and reliability as standard designs, but in a much smaller and lighter form factor.

Read more...
PCS stays up so you don’t have to
PCS Global System Integration & Control Systems Design
Maybe it’s time to look at a solution that stays online 99,99999% of the time so you don’t have to. This the world of Stratus computer platforms, tailor-made for your critical applications.

Read more...
Four ways the global parts shortage has led to innovation and openness
System Integration & Control Systems Design
For those who use automation parts, the unpredictable nature of the supply chain is one of the biggest problems faced today. The shortfall has impacted every industry, but automation components have been especially affected.

Read more...
New pilot-operated relief valve
Emerson Automation Solutions Valves, Actuators & Pump Control
Emerson has introduced a pilot-operated relief valve for installation on pressurised bullet tanks used to store liquid propane and anhydrous ammonia. This type of pressure relief valve is typically installed on tanks fabricated by OEMs for end users, engineering firms, or contractor customers.

Read more...
Pulse valves for dust collection
Emerson Automation Solutions Valves, Actuators & Pump Control
In process manufacturing, especially hard mineral mining, dust particles are unavoidable. If this pervasive dust is not effectively removed, it can accumulate throughout mines, plants and other facilities, becoming hazardous to workers and equipment.

Read more...
High-flow solenoid valve
Emerson Automation Solutions Valves, Actuators & Pump Control
Emerson has introduced the new ASCO Series 327C solenoid valve, which features a direct-acting, high-flow design that provides superior flow-to-power ratio. It permits high flows at minimum power levels, making it ideal for use in power plants, refineries, and chemical processing facilities.

Read more...
Iritron’s year of consolidation
Iritron Editor's Choice System Integration & Control Systems Design
Despite the multiple challenges faced by businesses in South Africa, the buoyancy of the technology sector worldwide has produced some green shoots for automation specialist, Iritron.

Read more...
Five edge opportunities for SIs to maximise revenue in 2024
Editor's Choice System Integration & Control Systems Design
System integrators continue to face the challenge of doing more with less – supporting complex operations, while meeting production schedules with limited resources, and innovating to increase efficiency, maximise safety and reduce risk.

Read more...