Editor's Choice


Case History 199: Another example of the effectiveness of cascade control

September 2025 Editor's Choice Fieldbus & Industrial Networking

In my last article, I wrote about how cascade control systems can effectively overcome valve problems. This article gives another example of how a temperature control was able to perform well, in spite of severe valve problems. The control in question used a cascaded secondary controller to control the flow of steam to a reboiler in a refinery. The temperature control was cycling, and we were requested to investigate this.

When analysing cascade controls one always starts with the secondary control loop, which in this case was the steam flow. Figure 1 is a closed loop ‘as found’ test, where one records the operation of the control in automatic prior to making any changes. In the recording one can see the operation of the flow with the controller’s set point in remote, i.e., it is connected to the output of the primary temperature controller. The first obvious thing that could be seen is that the set point was moving in a slow sinusoidal cycle.

To digress slightly, this was the problem which we had been requested to investigate and it was being caused by some external influence occurring on the column, and had nothing to do with problems in the actual temperature control. I will not be discussing this further in this article, but would just mention that the temperature control could not catch it, even with improved tuning, and it was decided that a further investigation needed to be carried out on the column to find out what was causing it.

The second thing that could be seen in the test was that the flow control was managing to keep the flow following the cycling set point fairly well, even though the flow seemed to jumping around quite badly and was itself cycling at times. However, these fluctuations would not have affected the actual temperature control as the temperature had much slower dynamics, which could not have reacted to the fluctuations as the correct average amount of heat would have been passed into the process.

An open loop test was then carried out on the flow control. This is the main type of test that one needs to really analyse the components of the loop and determine if problems exist. This test is shown in Figure 2, and is really a remarkable example of illustrating some severe final control element problems:

One of the most striking things shown is that the valve is massively oversized, probably by about a factor of 5. This can be seen by looking at the ratio of the step sizes of PV to PD, which should ideally be about unity. As discussed in previous articles oversized valves ‘multiply’ all valve problems by the oversize factor including control variance.

The next obvious thing is that the control element does not follow the PD signal very well and jumps about in a very inconsistent fashion. Good examples of this are illustrated in the figure, some examples being:

• The PV on one occasion went into a small cycle.

• On some steps, but not all, the PV would overshoot by several percent and then come back.

• On one occasion, when the PD was constant, the PV suddenly stepped up by several percent and remained there.

• On another occasion it did the same thing, but this time only returned to its original value after about 30 seconds.

• On one step of the PD, the PV initially moved the wrong way.

At the operating conditions, the PD was working at about 20%, which is quite low. This is because of the huge valve oversizing. As a general rule, this is about the minimum where valves should be allowed to operate under normal control conditions. The reasons of this have been discussed in previous articles.

What can one conclude from these observations? Firstly, if good control is required, a five times oversized valve is very bad, and secondly, control would be affected badly with the valve performance being so erratic. Thirdly, one can easily conclude that there is a huge problem within the valve-positioner combination.

Just in passing, a very important point is that in many modern plants one can get a so called ‘valve position’ feedback signal directly fed back into the control room from the modern smart valve positioners. In many cases such as this, the signal may not reflect the problems that were seen in the open loop flow test, and it would give the erroneous impression that the positioner was doing a great job. The reason for this is that most of the positioners actually measure the position of the actuator stem, and not the true valve position. Therefore, in many cases where there are linkages or other things like gears between the actuator and the actual valve, problems are not seen.

What would the control have been like if they had not used the flow cascaded onto the temperature, and had rather placed the valve directly onto the PD of the temperature controller?

The answer is that there would probably have been no proper control with the valve in the condition that it was. The reason for this is that the temperature process had very slow dynamics, with a time constant in the order of several minutes. As discussed previously, a general fact is that one can only control slow processes slowly or instability can result. Therefore, if one was to use the fastest possible temperature controller parameters on the temperature controller, it would have taken a long time to try and get the valve to pass the correct amount of steam into the process, and by that time the valve may have jumped again, and it would be likely that one would never be able to get the temperature to the desired set point.

However, one could control the flow process very much faster as it had dynamics with time constants in the order of just a couple of seconds, and therefore could more or less keep the flow close to setpoint. Figure 3 shows a recording performed after both the temperature and flow loops had been properly tuned. One can see the flow loop running firstly in remote setpoint, and then in local setpoint to see how it performed with step changes.

When the set point was constant, the flow was pretty close to setpoint in spite of the valve jumping around badly at times. However, the average flow would certainly be good enough to satisfy the requirements of the temperature controller. The flow also reacted very well to even large setpoint step changes. When the setpoint was changing in part of the sinusoidal cycle, the flow did lag by a few seconds, but this would still be good enough for the temperature control.

It is another excellent example of the power of cascade control to overcome serious final control element problems.



About Michael Brown

Michael Brown is a retired specialist in control loop optimisation, with over 50 years of experience in process control instrumentation. His main activities were consulting and teaching practical control loop analysis and optimisation. He presented courses and optimised controls in numerous plants in many countries around the world. Michael is continuing to write articles based on the work he has done, and his courses are still available for purchase in .PDF format. He is still handling the sales of the Protuner Loop Optimisation software. He is happy to answer questions people may have on loop problems.

Contact details: Michael Brown Control Engineering CC, +27 82 440 7790, michael.brown@mweb.co.za, www.controlloop.co.za


Credit(s)



Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

How to size and select a servo motor
Festo South Africa Editor's Choice Motion Control & Drives
Festo highlights some factors to consider in the process of sizing and selecting a servo motor effectively to ensure optimal performance, reliability and energy efficiency.

Read more...
Dynamic control of industrial solar plants and energy storage systems
Beckhoff Automation Editor's Choice Electrical Power & Protection
Spanish Group, Power Electronics has demonstrated its comprehensive expertise in sustainable energy supply in over 3000 solar and energy storage projects with a total installed capacity of 120 GW. To control its modular systems, the company relies on open, high-performance Beckhoff control technology.

Read more...
Loop signature Part 2-4: Feedforward Control: Part 3
Michael Brown Control Engineering Editor's Choice Fieldbus & Industrial Networking
In the previous articles in this series, the basic theory behind feedforward control was discussed, and it was also shown how to apply feedforward in practice. In this article, it will be shown how well feedforward can work in practice by giving a couple of examples.

Read more...
Engineers, AI and the risk of cognitive surrender
Editor's Choice
AI will have a significant impact on how engineering work gets done in the future, but the cognitive implications of continued AI use are serious.

Read more...
Reinventing grain silo management
VEGA Controls SA Editor's Choice
The VEGAPULS 6X radar sensor is designed for continuous level measurement to help overcome the challenges faced by storage in grain silos.

Read more...
Trends in humanoid robots
Editor's Choice
Humanoid robots are increasingly viewed less as futuristic prototypes and more as a practical route to bring artificial intelligence into human-designed environments.

Read more...
Four futures for AI: The choices we need to make now
Editor's Choice IT in Manufacturing
AI is everywhere and its implications are now structural. The question is no longer whether AI will matter, but what kind of society it will shape.

Read more...
Modular control platform for the hydrogen industry
Beckhoff Automation Editor's Choice Electrical Power & Protection
With a seamless modular control solution from Beckhoff featuring over 500 data points and numerous ELX series terminals with intrinsically safe interfaces, Greenlight Innovation is breaking new ground in hydrogen testing.

Read more...
Loop signature Part 2-3: Feedforward Control: Part 2
Michael Brown Control Engineering Editor's Choice Fieldbus & Industrial Networking
Feedforward control tuning is not nearly as critical as feedback tuning, and fairly simple models are usually fine for the purpose in hand.

Read more...
Proactive treatment of industrial boiler water
Editor's Choice
As water treatment is a critical aspect of industrial boiler management and potentially one of the greatest operational risk points, AES relies on close partnerships with third-party industrial water treatment specialists. These act as important safety nets.

Read more...









While every effort has been made to ensure the accuracy of the information contained herein, the publisher and its agents cannot be held responsible for any errors contained, or any loss incurred as a result. Articles published do not necessarily reflect the views of the publishers. The editor reserves the right to alter or cut copy. Articles submitted are deemed to have been cleared for publication. Advertisements and company contact details are published as provided by the advertiser. Technews Publishing (Pty) Ltd cannot be held responsible for the accuracy or veracity of supplied material.




© Technews Publishing (Pty) Ltd | All Rights Reserved